Common use of Extension of Performance Security Clause in Contracts

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 (two) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 32 contracts

Samples: Engineering, Procurement and Construction, Model Agreement, Draft Contract Agreement

AutoNDA by SimpleDocs

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of [2 (two) years]; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 10 contracts

Samples: And Construction Agreement, And Construction Agreement, And Construction Agreement

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of periodof [2 (two) years]; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 4 contracts

Samples: And Construction Agreement, And Construction Agreement, indianrailways.gov.in

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 (two) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority Employer shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 4 contracts

Samples: Procurement and Construction Agreement, Epc Contract Agreement, And Construction Agreement

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 (two) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority Employer shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 3 contracts

Samples: Epc Agreement, Epc Agreement, Procurement and Construction

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 3 (twothree) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: (Engineering Procurement and Construction

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 (two) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority Authority/GMDA shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: Engineering Procurement And

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 4 (twofour) yearsyears including defect liability period; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: Procurement and Construction Agreement

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 1 (twoOne) yearsyear; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 1 (twoone) months month prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security The performance security shall be deemed to be released and valid until the Authority shall return the same to the Contractor within a completion of Defect Liability Period or extended period of 7 (seven) business days from the date of submission of the extended Performance Securityif any.

Appears in 1 contract

Samples: Definitions and Interpretation

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period 12 It is different from Retention Money. of [2 (two) years]; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: Procurement and Construction Agreement

AutoNDA by SimpleDocs

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 (two) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority Employer shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: Contract Agreement

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 (two) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority SPV shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: www.nicdc.in

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 (two) years; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.Security.‌

Appears in 1 contract

Samples: Draft Contract Agreement

Extension of Performance Security. 7.2.1 The Contractor may initially provide the Performance Security for a period of [2 (two) years]; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 (two) months prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: Epc Agreement

Extension of Performance Security. The Contractor may initially provide the Performance Security for a period of 2 1 (twoOne) yearsyear; provided that it shall procure the extension of the validity of the Performance Security, as necessary, at least 2 1 (twoone) months month prior to the date of expiry thereof. Upon the Contractor providing an extended Performance Security, the previous Performance Security shall be deemed to be released and the Authority shall return the same to the Contractor within a period of 7 (seven) business days from the date of submission of the extended Performance Security.

Appears in 1 contract

Samples: smartcityraipur.cgstate.gov.in