Appropriation of Performance Security. (i) Upon occurrence of a Contractor’s Default, the Authority shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to encash and appropriate the relevant amounts from the Performance Security as Damages for such Contractor’s Default.
(ii) Upon such encashment and appropriation from the Performance Security, the Contractor shall, within 30 (thirty) days thereof, replenish, in case of partial appropriation, to its original level the Performance Security, and in case of appropriation of the entire Performance Security provide a fresh Performance Security, as the case may be, and the Contractor shall, within the time so granted, replenish or furnish fresh Performance Security as aforesaid failing which the Authority shall be entitled to terminate the Agreement in accordance with Article 23. Upon replenishment or furnishing of a fresh Performance Security, as the case may be, as aforesaid, the Contractor shall be entitled to an additional Cure Period of 30 (thirty) days for remedying the Contractor’s Default, and in the event of the Contractor not curing its default within such Cure Period, the Authority shall be entitled to encash and appropriate such Performance Security as Damages, and to terminate this Agreement in accordance with Article 23.
Appropriation of Performance Security. Upon occurrence of a Concessionaire Default or failure to meet any Condition Precedent, the Authority shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to encash and appropriate from the Performance Security the amounts due to it for and in respect of such Concessionaire Default or for failure to meet any Condition Precedent. Upon such encashment and appropriation from the Performance Security, the Concessionaire shall, within 15 (fifteen) days thereof, replenish, in case of partial appropriation, to the original level of the Performance Security, and in case of appropriation of the entire Performance Security provide a fresh Performance Security, as the case may be, failing which the Authority shall be entitled to terminate this Agreement in accordance with Article 31. Provided that upon appropriation on account of Concessionaire’s Default the Concessionaire shall replenish the Performance Security and upon such replenishment or furnishing of a fresh Performance Security, as the case may be, the Concessionaire shall be entitled to an additional Cure Period of 120 (one hundred and twenty) days for remedying the Concessionaire Default, save and except as provided in Clause 4.5 of this Agreement, and in the event of the Concessionaire not curing its default within such Cure Period, the Authority shall be entitled to encash and appropriate such Performance Security as Damages, and to terminate this Agreement in accordance with Article 31.
Appropriation of Performance Security. (i) Upon occurrence of a Contractor’s Default, the Authority shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to encash and appropriate the relevant amounts from the Performance Security as Damages for such Contractor’s Default.
Appropriation of Performance Security. (a) In the event of the Concessionaire being in default of the due, faithful and punctual performance of its obligations under the RFP, the LoA, and under Section 3.4 of this Agreement and during the Construction Period and until the date of issue of the Completion Certificate in respect of all the Project Facilities under MDOs, as the case may be, or owning any sums whatsoever to Authority under this Agreement or in the event of there being any claims or demands whatsoever whether liquidated or which may at any time be made or have been made on behalf of the Authority for or against the Concessionaire under this Agreement or against the Authority in respect of this Agreement, the Authority shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to call in, encash and appropriate the relevant or delinquent amounts from the Performance Security as damages for such default, dues, demands or claims.
(b) The decision of the Authority as to any breach/delay having been committed, liability accrued or loss or damage caused or suffered shall be conclusive, absolute and binding on the Concessionaire. The Concessionaire specifically confirms and agrees that no proof of any amount of liability accrued or loss or damages caused or suffered by the Authority under this Agreement is required to be provided in connection with any demand made by the Authority to recover such compensation through encashment of the Performance Security under this Agreement and that no document or any action shall be required other than the Authority’s written demand as aforesaid.
(c) In the event of encashment of the Performance Security by the Authority, in full or part, the Concessionaire shall within 30 (thirty) days of receipt of the encashment notice from the Authority provide a fresh Performance Security or replenish the existing Performance Security to its original value, as the case may be. The provisions of this Article 9 shall apply mutatis mutandis to such fresh Performance Security. The Concessionaire’s failure to comply with this provision shall constitute a concessionaire Event of Default, which shall entitle the Authority to terminate this Agreement in accordance with the provisions of Article 16 hereof.
Appropriation of Performance Security. Upon occurrence of a Aggregator Default or failure to meet any Condition Precedent, the Utility shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to encash and appropriate from the Performance Security the amounts due to it for and in respect of such Aggregator Default or for failure to meet any Condition Precedent. Upon such encashment and appropriation from the Performance Security, the Aggregator shall, within 15 (fifteen) days thereof, replenish, in case of partial appropriation, to the original level of the Performance Security, and in case of appropriation of the entire Performance Security provide a fresh Performance Security, as the case may be, failing which the Utility shall be entitled to terminate this Agreement in accordance with Article 17. Upon such replenishment or furnishing of a fresh Performance Security, as the case may be, the Aggregator shall be entitled to an additional Cure Period of 120 (one hundred and twenty) days for remedying the Aggregator Default or to meet any Condition Precedent, and in the event of the Aggregator not curing its default or meeting such Condition Precedent within such Cure Period, the Utility shall be entitled to encash and appropriate the Performance Security as Damages, and to terminate this Agreement in accordance with Article 17.
Appropriation of Performance Security. (i) Upon occurrence of a Contractor’s Default, the Authority shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to encash and appropriate the relevant amounts from the Performance Security as Damages for such Contractor’s Default.
(ii) Upon such encashment and appropriation from the Performance Security, the Contractor shall, within 30 (thirty) days thereof, replenish, in case of partial appropriation, to its original level the Performance Security, and in case of appropriation of the entire Performance Security provide a fresh Performance Security, as the case may be, and the Contractor shall, within the time so granted, replenish or furnish fresh Performance Security as aforesaid failing which the Authority shall be entitled to terminate the Agreement in accordance with Article
Appropriation of Performance Security. Upon occurrence of a Supplier Default or failure to meet any Condition Precedent, the Utility shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to encash and appropriate from the Performance Security the amounts due to it for and in respect of such Supplier Default or for failure to meet any Condition Precedent. Upon such encashment and appropriation from the Performance Security, the Supplier shall, within 15 (fifteen) days thereof, replenish, in case of partial appropriation, to the original level of the Performance Security, and in case of appropriation of the entire Performance Security provide a fresh Performance Security, as the case may be, failing which the Utility shall be entitled to terminate this Agreement in accordance with Article 19. Upon such replenishment or furnishing of a fresh Performance Security, as the case may be, the Supplier shall be entitled to an additional Cure Period of 120 (one hundred and twenty) days for remedying the Supplier Default or to meet any Condition Precedent, and in the event of the Supplier not curing its default or meeting such Condition Precedent within such Cure Period, the Utility shall be entitled to encash and appropriate the Performance Security as Damages, and to terminate this Agreement in accordance with Article 19. £To be calculated @ Rs. 10,00,000 (Rs. ten lakh) per MW of Contracted Capacity.
Appropriation of Performance Security. 9.2.1 Upon occurrence of a Concessionaire Default or failure to meet any Condition Precedent, the Authority shall, without prejudice to its other rights and remedies hereunder or in law, be entitled to encash and appropriate the relevant amounts from the Performance Security, as the case may be, as Damages for such Concessionaire Default or failure to meet any Condition Precedent. Upon such encashment and appropriation from the Performance Security, the Concessionaire shall, within 15 (fifteen) days thereof, replenish, in case of partial appropriation, to its original level the Performance Security, and in case of appropriation of the entire Performance Security provide a fresh Performance Security, as the case may be, and the Concessionaire shall, within the time so granted, replenish or furnish fresh Performance Security as aforesaid failing which the Authority shall be entitled to terminate this Agreement in accordance with ARTICLE 25.
Appropriation of Performance Security. 9.2.1. Upon the occurrence of a Concessionaire Default or failure to meet any Condition Precedent, the Authority shall, without prejudice to its other rights and remedies hereunder be entitled to encash and appropriate the relevant amounts from the Performance Security as Damages for such Concessionaire Default or failure to meet any Condition Precedent. Upon such encashment and appropriation of the Performance Security, the Authority shall grant a period of 30 (thirty) days to the Concessionaire to provide either a fresh Performance Security or replenish, through another guarantee, the part amount so encashed failing which Authority shall, notwithstanding anything contained in this Agreement relating to Termination, be entitled to Terminate this Agreement in accordance with Article 21.
Appropriation of Performance Security. Upon occurrence of a Solar Power Developer Default or failure to meet the Conditions Precedent by the Solar Power Developer, APDCL shall, without prejudice to its other rights and remedies hereunder or in law, shall be entitled to encash and appropriate the relevant amounts from the Performance Security as Damages for such Solar Power Developer Default or Conditions Precedent. Upon such encashment and appropriation from the Performance Security, the Solar Power Developer shall, within 30 (thirty) days thereof, replenish, in case of partial appropriation, to its original level the Performance Security, and in case of appropriation of the entire Performance Security provide a fresh Performance Security, as the case may be, and the Solar Power Developer shall, within the time so granted, replenish or furnish fresh Performance Security as aforesaid failing which APDCL shall be entitled to terminate this Agreement in accordance with Article 16. Any penalty paid so, shall be returned to the SPD without any interest on achievement of successful commissioning within the SCD.