Facility Interconnection and Deliverability Requirements. Mesquite Solar 3 will utilize an existing interconnection comprised of two 500 kV generation tie lines between the Hassayampa Switchyard and the Mesquite 230/500 kV Switchyard.5 Together, the Hassayampa Switchyard, Palo Verde Switchyard, and three bus ties between the two switchyards form the Common Bus at Palo Verde.6 Two 500 kV transmission lines under CAISO operational control are connected to the Common Bus: the Hassayampa-Hoodoo Wash line and the Palo Verde-Xxxxxx line.
Appears in 2 contracts
Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
Facility Interconnection and Deliverability Requirements. Mesquite Solar 3 5 will utilize an existing interconnection comprised of two 500 kV generation tie lines between the Hassayampa Switchyard and the Mesquite 230/500 kV Switchyard.5 Switchyard.6 Together, the Hassayampa Switchyard, Palo Verde Switchyard, and three bus ties between the two switchyards form the Common Bus at Palo Verde.6 Verde.7 Two 500 kV transmission lines under CAISO operational control are connected to the Common Bus: the Hassayampa-Hoodoo Wash line and the Palo Verde-Xxxxxx Devers line.
Appears in 1 contract
Facility Interconnection and Deliverability Requirements. Mesquite Solar 3 2 will utilize an existing interconnection comprised of two 500 kV generation tie lines between the Hassayampa Switchyard and the Mesquite 230/500 kV Switchyard.5 Switchyard.4 Together, the Hassayampa Switchyard, Palo Verde Switchyard, and three bus ties between the two switchyards form the Common Bus at Palo Verde.6 Verde.5 Two 500 kV transmission lines under CAISO operational control are connected to the Common Bus: the Hassayampa-Hoodoo Wash line and the Palo Verde-Xxxxxx line.
Appears in 1 contract