FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 11 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner Manager does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven (7) additional days’ written notice to the OwnerManager, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-shut- down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 2 contracts
Samples: Design Build Agreement, Design Build Agreement
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for PaymentPayment regarding undisputed amounts, through no fault of the Design-Design- Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven fourteen (14) additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner Manager does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven (7) additional days’ written notice to the OwnerManager, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-BuilderDesign -Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received, unless the Design Builder and Owner agree otherwise. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner Manager does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven (7) additional days’ written notice to the Owner, Manager, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven additional thirty (30)additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-Builder, Architect, Consultants, or Contractors, within the time required by the Design-Build Documents, then the Design-Builder may, upon seven additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum Guaranteed Maximum Price shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Design Build Contract
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-Builder, within the time required by the Design-Build Documentsnoted herein, then the Design-Builder may, upon seven additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-Builder’s reasonable costs of shut-down, delay and start-up, plus interest as provided for in the Design-Build Documents.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder (Fox Factory Holding Corp)
FAILURE OF PAYMENT. If the Owner does not issue a Certificate for Payment, through no fault of the Design-BuilderContractor, Designer, Consultants, or Contractors, within the time required by the Design-Build Contract Documents, then the Design-Builder Contractor may, upon seven 7 additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Design-BuilderContractor’s reasonable costs of shut-shut- down, delay and start-up, plus interest as provided for in the Design-Build Contract Documents.
Appears in 1 contract
Samples: Engineering, Procurement, and Construction Agreement