Field Representatives’ Meeting Sample Clauses
The Field Representatives’ Meeting clause establishes the requirement for regular meetings between representatives from each party involved in a project or contract. These meetings typically serve as a forum to discuss project progress, address operational issues, and coordinate activities on-site. By mandating such meetings, the clause ensures ongoing communication, facilitates problem-solving, and helps prevent misunderstandings or delays during the execution of the project.
Field Representatives’ Meeting. Within five days (5) after a dispute or claim occurs, the Design-Builder’s senior project management personnel who have authority to resolve the dispute or claim shall meet with the Owner’s project representative who has authority to resolve the dispute or claim in a good faith attempt to resolve the dispute or claim. If a party intends to be accompanied at a meeting by legal counsel, the other party shall be given at least three (3) working days’ notice of such and also may be accompanied by legal counsel. All negotiations pursuant to this clause are confidential and shall be treated as compromise and settlement negotiations for purposes of rules of evidence.
Field Representatives’ Meeting. Within fifteen (15) Business Days after notice of the Dispute, ENGIE Services U.S.’s senior project management personnel will meet with District’s project representative in a good faith attempt to resolve the Dispute.
Field Representatives’ Meeting. Within fifteen (15) Business Days after notice of the Dispute, Chevron Energy Solutions’ senior project management personnel will meet with Manhattan Beach USD’s project representative in a good faith attempt to resolve the Dispute.
Field Representatives’ Meeting. Within fifteen (15) Business Days after notice of the Dispute, OpTerra Energy Services’ senior project management personnel will meet with ConFire’s project representative in a good faith attempt to resolve the Dispute.
Field Representatives’ Meeting. Within fifteen (15) Business Days after notice of the Dispute, ENGIE Services U.S.’s senior project management personnel will meet with Dublin USD’s project representative in a good faith attempt to resolve the Dispute.
Field Representatives’ Meeting. Within fifteen (15) business days after notice of the Dispute, OpTerra ESs’ senior project management personnel will meet with Customer’s project representative in a good faith attempt to resolve the Dispute.
Field Representatives’ Meeting. Within fifteen (15) days after one Party’s written notice of the Dispute to the other Party, ESG’s project manager shall meet with Subcontractor’s project representative in a good faith attempt to resolve the Dispute.