FINAL COMPLETION AND FINAL PAYMENT. § 12.6.1 Upon receipt of a final Application for Payment, the Architect will inspect the Work. When the Architect finds the Work acceptable and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment. § 12.6.2 Final payment shall not become due until the Contractor submits to the Architect releases and waivers of liens, and data establishing payment or satisfaction of obligations, such as receipts, claims, security interests, or encumbrances arising out of the Contract. § 12.6.3 Acceptance of final payment by the Contractor, a subcontractor or supplier shall constitute a waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment.
Appears in 9 contracts
Samples: Standard Short Form of Agreement Between Owner and Contractor, Standard Short Form of Agreement Between Owner and Contractor, Standard Short Form of Agreement Between Owner and Contractor
FINAL COMPLETION AND FINAL PAYMENT. § 12.6.1 Upon receipt of a final Application for Payment, the Architect will inspect the Work. When the Architect finds the Work acceptable and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment.
§ 12.6.2 Final payment shall not become due until the Contractor submits to the Architect releases and waivers of liens, and data establishing payment or satisfaction of obligations, such as receipts, claims, security interests, interests or encumbrances arising out of the Contract.
§ 12.6.3 Acceptance of final payment by the Contractor, a subcontractor or material supplier shall constitute a waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment.
Appears in 3 contracts
Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project
FINAL COMPLETION AND FINAL PAYMENT. § 12.6.1 Upon receipt of a final Application for Payment, the Architect will inspect the Work. When the Architect finds the Work acceptable and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment.
§ 12.6.2 Final payment shall not become due until the Contractor submits to the Architect releases and waivers of liens, and data establishing payment or satisfaction of obligations, such as receipts, claims, security interests, certified payroll reports or encumbrances arising out of the Contract.
§ 12.6.3 Acceptance of final payment by the Contractor, a subcontractor or supplier shall constitute a waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment.
Appears in 1 contract
Samples: Standard Short Form of Agreement Between Owner and Contractor
FINAL COMPLETION AND FINAL PAYMENT. § 12.6.1 11.6.1 Upon receipt of a final Application for Payment, the Architect Owner will inspect the Work. When the Architect Owner finds the Work acceptable and the Contract fully performed, the Architect Owner will promptly issue a final Certificate for Payment.
§ 12.6.2 11.6.2 Final payment shall not become due until the Contractor submits to the Architect Owner releases and waivers of liens, and data establishing payment or satisfaction of obligations, such as receipts, claims, security interests, or encumbrances arising out of the Contract.
§ 12.6.3 11.6.3 Acceptance of final payment by the Contractor, a subcontractor or supplier shall constitute a waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment.
Appears in 1 contract
Samples: Construction Contract
FINAL COMPLETION AND FINAL PAYMENT. § 12.6.1 Upon receipt of a final Application for Payment, the Architect CM/PM will inspect the Work. When the Architect CM/PM finds the Work acceptable and the Contract fully performed, the Architect CM/PM will promptly issue a final Certificate for Payment.
§ 12.6.2 Final payment shall not become due until the Contractor submits to the Architect CM/PM releases and waivers of liens, and data establishing payment or satisfaction of obligations, such as receipts, claims, security interests, or encumbrances arising out of the Contract.
§ 12.6.3 Acceptance of final payment by the Contractor, a subcontractor or supplier shall constitute a waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment.
Appears in 1 contract
Samples: Standard Short Form of Agreement Between Owner and Contractor