Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer: (a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4; (b) the amounts received from the Authority against each claim; and (c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority: (i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or (ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items. 19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 16 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Final Payment Statement. 19.13.1 (i) Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.412.2, the Contractor shall submit to the Authority’s Engineer for consideration six 6 (six) copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) i. an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) . a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 (ii) If the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 19.13 (i) within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 5 contracts
Samples: Engineering Procurement and Construction (Epc) Contract, Engineering Procurement and Construction (Epc) Contract, Engineering Procurement and Construction Agreement
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Authority‟s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Authority‟s Engineer:
(a) the summary of Contractor’s Contractor‟s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Authority‟s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Authority‟s Engineer may reasonably require. The Authority’s Authority‟s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Authority‟s Engineer does not prescribe the form referred to in Clause 19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 4 contracts
Samples: Engineering, Procurement and Construction Agreement, Epc Agreement, Construction Contract
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the The summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the The amounts received from the Authority against each claim; and
(c) any Any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 3 contracts
Samples: Contract Agreement, Contract Agreement, Contract Agreement
Final Payment Statement. 19.13.1 17.10.1 Within 60 (sixty) days after of receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Authority Engineer for consideration six copies of a Final Payment Statement final payment statement (the “Final Payment Statement”) for Works), with supporting documents showing in detaildocuments, in the form prescribed by the Authority’s Authority Engineer:
(a) the summary of Contractor’s Stage Payment claims Statements for Works as submitted in accordance with Clause 19.417.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. .
17.10.2 If the Authority’s Authority Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Authority Engineer may reasonably require. The Authority’s Authority Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 2624; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 17.15, if there are no disputed items.
19.13.2 17.10.3 If the Authority’s Authority Engineer does not prescribe the form referred to in Clause 19.13.1 17.10.1 within 15 7 (fifteenSeven) days of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 3 contracts
Samples: Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement, Epc Agreement
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause Clause
19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 3 contracts
Samples: Draft Contract Agreement, Epc Agreement, Epc Agreement
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the AuthorityEmployer’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the AuthorityEmployer’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority Employer against each claim; and
(c) any further sums which the Contractor considers due to it from the AuthorityEmployer. If the AuthorityEmployer’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the AuthorityEmployer’s Engineer may reasonably require. The AuthorityEmployer’s Engineer shall deliver to the AuthorityEmployer:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the AuthorityEmployer’s Engineer does not prescribe the form referred to in Clause 19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 3 contracts
Samples: Demonstration Agreement, Epc Agreement, Contract Agreement for Design and Construction
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in notin dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; orbe
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause Clause
19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 3 contracts
Samples: Epc Agreement, Epc Agreement, Epc Agreement
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Final Payment Statement. 19.13.1 17.10.1 Within 60 (sixty) days after of receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement final payment statement (the “Final Payment Statement”) for Works), with supporting documents showing in detaildocuments, in the form prescribed by the Authority’s EngineerEngineer in respect of:
(a) the summary of Contractor’s Stage Payment claims for Works Statements as submitted in accordance with Clause 19.417.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. .
17.10.2 If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. .
17.10.3 The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 2624; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 17.15, if there are no disputed items.
19.13.2 If 17.10.4 In the event that the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 17.10.1 within 15 7 (fifteenseven) days of the date of issue of the a Completion Certificate, the Contractor shall submit the statement in such form as it deems may reasonably deem fit.
Appears in 2 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 19.13.3 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 1 contract
Samples: Draft Agreement for RFP for Beautification of Streets
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Authority‟s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Authority‟s Engineer:
(a) the summary of Contractor’s Contractor‟s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Authority‟s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Authority‟s Engineer may reasonably require. The Authority’s Authority‟s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Authority‟s Engineer does not prescribe the form referred to in Clause Clause
19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 1 contract
Samples: Draft Contract Agreement
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) i. an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) . a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause Clause
19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 1 contract
Samples: Epc Agreement
Final Payment Statement. 19.13.1 (i) Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.412.2, the Contractor shall submit to the Authority’s 's Engineer for consideration six 6 (six) copies of a Final Payment Statement (the “"Final Payment Statement”") for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s 's Engineer:
(a) the summary of Contractor’s 's Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s 's Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s 's Engineer may reasonably require. The Authority’s 's Engineer shall deliver to the Authority:
(i) i. an IPC I PC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) . a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 (ii) If the Authority’s 's Engineer does not prescribe the form referred to in Clause 19.13.1 19.13 (i) within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 1 contract
Samples: Construction Contract
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in notin dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; or
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 1 contract
Samples: Epc Agreement
Final Payment Statement. 19.13.1 Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.4, the Contractor shall submit to the Authority’s Engineer for consideration six copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) an IPC for those parts of the Final Payment Statement which are not in dispute, along with a list of disputed items which shall then be settled in accordance with the provisions of Article 26; orbe
(ii) a Final Payment Certificate in accordance with Clause 19.15 if there are no disputed items.
19.13.2 If the Authority’s Engineer does not prescribe the form referred to in Clause Clause
19.13.1 within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 1 contract
Samples: Epc Agreement
Final Payment Statement. 19.13.1 (i) Within 60 (sixty) days after receiving the Completion Certificate under Clause 12.412.2, the Contractor shall submit to the Authority’s Engineer for consideration six 6 (six) copies of a Final Payment Statement (the “Final Payment Statement”) for Works, with supporting documents showing in detail, in the form prescribed by the Authority’s Engineer:
(a) the summary of Contractor’s Stage Payment claims for Works as submitted in accordance with under Clause 19.4;
(b) the amounts received from the Authority against each claim; and
(c) any further sums which the Contractor considers due to it from the Authority. If the Authority’s Engineer disagrees with or cannot verify any part of the Final Payment Statement, the Contractor shall submit such further information as the Authority’s Engineer may reasonably require. The Authority’s Engineer shall deliver to the Authority:
(i) i. an IPC for those parts of the Final Payment Statement which that are not in dispute, along with a list of disputed items which that shall then be settled in accordance with under the provisions of Article 26; or
(ii) . a Final Payment Certificate in accordance with under Clause 19.15 if there are no disputed items.
19.13.2 (ii) If the Authority’s Engineer does not prescribe the form referred to in Clause 19.13.1 19.13 (i) within 15 (fifteen) of the date of issue of the Completion Certificate, the Contractor shall submit the statement in such form as it deems fit.
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Agreement