Force Majeure Delays. For purposes of this Work Letter, "Force Majeure Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.
Appears in 2 contracts
Samples: Office Building Lease (California First National Bancorp), Industrial Lease (Cutter & Buck Inc)
Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.
Appears in 2 contracts
Samples: Office Building Lease (Virtual Mortgage Network Inc), Office Building Lease (New Century Financial Corp)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 19(v) of the Lease.
Appears in 1 contract
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay beyond the reasonable control and not the fault of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 19(w) of the Lease.
Appears in 1 contract
Force Majeure Delays. For purposes of this Work LetterLetter Agreement, "“Force Majeure Delays" ” means any actual delay in the construction of the Tenant Improvements, which Improvements that is beyond the reasonable control of Landlord or Tenant, as the case may be. Notwithstanding the foregoing, as described in Paragraph 33 delays or failures to perform resulting from lack of funds shall not be deemed delays beyond the Leasereasonable control of a party.
Appears in 1 contract
Samples: Lease (CombiMatrix Corp)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" ” means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as “Force Majeure” is described in Paragraph 33 Section 26.03 of the Lease.. Exhibit C-1
Appears in 1 contract
Samples: Lease (Adamas Pharmaceuticals Inc)
Force Majeure Delays. For purposes of this Work Letter, "Force -------------------- Majeure Delays" means any actual delay in the construction of the Expansion Space Tenant Improvements, Improvements (including required Building permits) which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.
Appears in 1 contract
Samples: Office Building Lease (Interplay Entertainment Corp)
Force Majeure Delays. For purposes of this Work Letter, "Force Majeure Delays" means shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by many of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 32.15 of the Lease.
Appears in 1 contract
Samples: Office Lease (Willdan Group, Inc.)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by many of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 38 of the Lease.
Appears in 1 contract
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord in the construction of any of the Office Improvements or Tenantthe Allowance Improvements, as which is not a Tenant Delay and which is caused by any of the case may be, as causes described in Paragraph 33 Section 31.17 of the Lease.
Appears in 1 contract
Samples: Commercial Lease (Gigamon LLC)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 19(w) of the Lease.
Appears in 1 contract
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 26.03 of the Lease.
Appears in 1 contract
Samples: Office Lease Agreement (Exponential Interactive, Inc.)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 29.17 of the Original Lease..
Appears in 1 contract
Samples: Office Lease (XOMA Corp)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 31.17 of the LeaseStandard Provisions.
Appears in 1 contract
Samples: Commercial Lease (Boxabl Inc.)
Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, permits) which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.
Appears in 1 contract
Samples: Office Building Lease (Interplay Entertainment Corp)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" ” means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 Section 31.17 of the LeaseStandard Provisions.
Appears in 1 contract
Samples: Office Lease (Alteryx, Inc.)
Force Majeure Delays. For purposes of this Work Letter, "“Force Majeure Delays" ” means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as “Force Majeure” is described in Paragraph 33 Section 26.03 of the Lease.
Appears in 1 contract
Samples: Lease (Adamas Pharmaceuticals Inc)
Force Majeure Delays. For purposes of this Work Letter, "Force Majeure Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 Section 32.15 of the Lease.
Appears in 1 contract
Samples: Office Lease (Silicon Image Inc)
Force Majeure Delays. For purposes of this Tenant Work Letter, "“Force Majeure Delays" ” means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 Section 29.16 of the Lease.
Appears in 1 contract
Force Majeure Delays. For purposes of this Work Letter, "Force Majeure Delays" means shall mean any actual delay beyond the reasonable control of Lessor in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 28.D of the Lease.
Appears in 1 contract
Samples: Standard Industrial/Commercial Multi Tenant Lease Net (Socket Communications Inc)