Common use of Generation Compensation in offtake constraints due to Grid Unavailability Clause in Contracts

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 11 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation from buying utility shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 8 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Sale Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Wind Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 4 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Wind Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to and payable by the following Buying Utility(ies) as under and there shall be no other claim, directly or indirectly against SECI:

Appears in 3 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Hybrid Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation from Buying Entity shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 3 contracts

Samples: Power Sale Agreement, Power Sale Agreement, Power Sale Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Wind Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation from buying utility shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 3 contracts

Samples: Power Sale Agreement, Power Sale Agreement, Power Sale Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project plant can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Wind Power Developer. In such cases, subject to the submission of documentary evidences evidence from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECIEDA&N:

Appears in 1 contract

Samples: Power Purchase Agreement

AutoNDA by SimpleDocs

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, unavailability the power is not evacuated, for reasons not attributable to the Solar Wind Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation from Buying Entity shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 1 contract

Samples: Power Sale Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECIMAHAGENCO:

Appears in 1 contract

Samples: Power Purchase Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Hybrid Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:

Appears in 1 contract

Samples: Power Purchase Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECIJDA:

Appears in 1 contract

Samples: Power Purchase Agreement

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECIBBMB:

Appears in 1 contract

Samples: Power Purchase Agreement