Generation Interconnection Request Requirements. For Transmission Provider to consider an Application for a Generation Interconnection Request complete, Applicant must include at a minimum each of the following, as further described in the Application and PJM Manuals: a. Provide all Applicant information required in the Application, including parent company information and banking and wire transfer information. b. Specify the location of the proposed Point of Interconnection to the Transmission System, including the substation name or the name of the line to be tapped (including the voltage), the estimated distance from the substation endpoints of a line tap, address, and GPS coordinates.
Appears in 5 contracts
Samples: Generation Interconnection Procedure, Generation Interconnection Procedure, Generation Interconnection Procedures