Handback Inspections. The Contractor and the Province shall jointly carry out the following handback inspections (consisting of all appropriate examinations and tests, carried out in accordance with all applicable Technical Requirements) in order to assess what work (including, in the case of the New Infrastructure, major rehabilitation work as required) is likely to be required in order to achieve the Handback Requirements: (a) the first handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is at least 57 months and not more than 63 months prior to expiry of the Term; (b) the second handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is at least 15 months and not more than 18 months prior to expiry of the Term; and (c) the third handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is not more than one month prior to the expiry of the Term.
Appears in 5 contracts
Samples: Design, Build, Finance and Operate Agreement, Dbfo Agreement, Design, Build, Finance and Operate Agreement
Handback Inspections. β The Contractor and the Province shall jointly carry out the following handback inspections (consisting of all appropriate examinations and tests, carried out in accordance with all applicable Technical Requirements) in order to assess what work (including, in the case of the New Infrastructure, major rehabilitation work as required) is likely to be required in order to achieve the Handback Requirements:
(a) the first handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is at least 57 months and not more than 63 months prior to expiry of the Term;
(b) the second handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is at least 15 months and not more than 18 months prior to expiry of the Term; and
(c) the third handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is not more than one month prior to the expiry of the Term.
Appears in 1 contract
Handback Inspections. The Contractor and the Province shall jointly carry out the following handback inspections (consisting of all appropriate examinations and tests, carried out in accordance with all applicable Technical Requirements) in order to assess what work (includingwork, in the case of the New Infrastructure, including major rehabilitation renewal work as required) , is likely to be required in order to achieve the Handback Requirements:
(a) the first handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is at least 57 months and not more than 63 months prior to expiry of the Term;
(b) the second handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is at least 15 28 months and not more than 18 34 months prior to expiry of the Term; and
(c) the third handback inspection shall take place at a time, specified by the Province following consultation with the Contractor, that is not more than one month prior to the expiry of the Term.
Appears in 1 contract