HOT WORK PROJECT PLANNING. Hot work may be conducted as a repair measure or on larger scale during construction or tenant buildouts. Historically, hot work operations have contributed significantly in large loss fires. In order to prevent losses, the following guidelines are provided for your consideration in managing hot work projects: 1. If possible, hot work should be scheduled for periods when the building is unoccupied. 2. Plan all work to minimize the exposure to fire. If possible, remove and relocate system/equipment component(s) to be worked on to an exterior area or an area designed for hot work.
Appears in 4 contracts
Samples: Lease Agreement (Irobot Corp), Lease Agreement (Irobot Corp), Lease Agreement (Irobot Corp)
HOT WORK PROJECT PLANNING. Hot work may be conducted as a repair measure or on larger scale during construction or tenant buildouts. Historically, hot work operations have contributed significantly in large loss fires. In order to prevent losses, the following guidelines are provided for your consideration in managing hot work projects:
1. If possible, hot work should be scheduled for periods when the building is unoccupied.
2. Plan all work to minimize the exposure to fire. If possible, remove and relocate system/equipment component(s) to be worked on to an exterior area or an area designed for hot work.
Appears in 1 contract
Samples: Lease Agreement (Irobot Corp)