Common use of Incomplete Works Clause in Contracts

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 95 contracts

Samples: Construction Contract, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement

AutoNDA by SimpleDocs

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 38 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 24 contracts

Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction Agreement, Contract Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.121.1.

Appears in 16 contracts

Samples: Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement, Epc Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority Employer in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority Employer under this Agreement including the right to termination under Clause 23.1.

Appears in 6 contracts

Samples: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time anyTime Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.121.1.

Appears in 6 contracts

Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour Endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 3 contracts

Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement

Incomplete Works. 10.5.1 In the event the Contractor fails to complete the Works in accordance with the Project Completion Commissioning Schedule, including any Time Extension granted under this Contract Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Contract Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Contract Agreement to take appropriate action against the Contractor including the right to termination under Clause 23.121.1.

Appears in 2 contracts

Samples: Draft Contract Agreement, Contract Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour endeavor to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 2 contracts

Samples: Epc Agreement, Draft Agreement for RFP for Beautification of Streets

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority SPV in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority SPV under this Agreement including the right to termination under Clause 23.121.1.

Appears in 1 contract

Samples: Epc Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority Employer in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority Employer under this Agreement including the right to termination under Clause 23.1.

Appears in 1 contract

Samples: Demonstration Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 1 contract

Samples: Construction Contract

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour Endeavour to complete the balance work expeditiously and shall pay Damages to the Authority Authority/GMDA in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority Authority/GMDA under this Agreement including the right to termination under Clause 23.1.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

AutoNDA by SimpleDocs

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii10.3.(ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.. P a g e | 60

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay shallpay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay fordelay of each day until the Works are completed in accordance with the provisions of this ofthis Agreement. Recovery of Damages under this Clause shall be without prejudice to the tothe rights of the Authority under this Agreement including the right to termination under Clause 23.1. 10.7 MaintenanceManual

Appears in 1 contract

Samples: Construction Contract

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery Improvement and widening to two lane with paved shoulder of Damages under this Clause shall be without prejudice road from Km 21.100 to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.Km

Appears in 1 contract

Samples: Contract Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time anyTime Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 1 contract

Samples: Epc Agreement

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.. Page 63 of 144

Appears in 1 contract

Samples: Construction Contract

Incomplete Works. In the event the Contractor fails to complete the Works in accordance with under the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour endeavor to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with under the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with under the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Agreement