Infrastructure. 1) The Developer shall submit the Infrastructure Improvements plans and application for right-of-way permits to construct the Infrastructure Improvements to the City’s Department of Public Works along with proposed utility easements by May 1, 2019. 2) The Developer shall submit proof reasonably satisfactory to the City of financing that is adequate to complete the Infrastructure Improvements and the proposed form of bond as required by Section II, Infrastructure Improvements, Paragraph h), Permits and Performance Bonds (the “Performance Bond”), for completion of the Infrastructure Improvements to the City’s Department of Planning, Building and Development after submittal of the Infrastructure Improvements plans, if permits have been issued by the Department of Public Works. 3) Within four (4) weeks from receipt, the City shall review submissions of the Infrastructure Improvements plans, the application for right-of-way permits, proposed construction easements, and the Performance Bond and either issue permit and approval notification or notify the Developer of any deficiencies. This time period shall be extended for any required review by any State Department or Agency. If deficiencies are noted, the Developer shall cure the deficiencies, and within two (2) weeks of the submission of any documentation to cure the deficiencies, the City shall advise the Developer of any deficiencies. Submission and review shall be repeated until no further deficiencies are noted. 4) The City shall grant construction easements to the Developer on the City’s standard forms, within 2 weeks of notification of approval of the plans. 5) Prior to the start of construction, the Developer shall submit the Performance Bond as required by Section II. The Developer shall begin construction of the Infrastructure Improvements within 4 weeks of issuance of permits and easements. 6) The Developer shall complete construction of the Infrastructure Improvements within 24 months of issuance of permits, and dedicate the Infrastructure Improvements and convey the utilities with required easements within 2 months thereafter.
Appears in 3 contracts
Samples: Development Agreement, Development Agreement, Development Agreement
Infrastructure. 1i) The Developer shall submit the Infrastructure Improvements plans and specifications, and application for right-of-way permits to construct the Infrastructure Improvements to the City’s Department of Public Works along with proposed utility easements by May 1, 201920 .
2ii) The Developer shall submit proof reasonably satisfactory to the City of financing that is adequate to complete the Infrastructure Improvements and the proposed form of bond as required by Section II, Infrastructure Improvements, Paragraph h), Permits and Performance Bonds (the “Performance Bond”), for completion of the Infrastructure Improvements to the City’s Department of Planning, Building and Development after submittal of the Infrastructure Improvements plans, if and prior to permits have been being issued by the Department of Public Works.
3iii) Within four (4) weeks 30 days from receipt, the City shall review submissions of the Infrastructure Improvements plans, the application for right-of-way permits, proposed construction easements, and the Performance Bond and either issue permit and approval notification or notify the Developer of any deficiencies. This time period shall be extended for any required review by any State Department or Agency. If deficiencies are noted, the Developer shall cure the deficiencies, and within two (2) weeks 14 days of the submission of any documentation to cure the deficiencies, the City shall advise the Developer of any deficiencies. Submission and review shall be repeated until no further deficiencies are noted.
4iv) The City shall grant construction easements to the Developer on the City’s standard forms, within 2 weeks 14 days of notification of approval of the Infrastructure Improvement plans.
5v) Prior to the start of construction, the Developer shall submit the Performance Bond as required by Section IIabove. The Developer shall begin construction of the Infrastructure Improvements within 4 weeks of issuance of permits and easements.
6vi) The Developer shall complete construction of the Infrastructure Improvements within 24 months of issuance of permits, and dedicate the Infrastructure Improvements and convey the utilities with required easements within 2 months thereafter.
Appears in 1 contract
Samples: Development Agreement
Infrastructure. 1) The Developer shall submit the Infrastructure Improvements plans and application for right-of-way permits to construct the Infrastructure Improvements to the City’s Department of Public Works along with proposed utility easements by May 1, 2019.
2) The Developer shall submit proof reasonably satisfactory to the City of financing that is adequate to complete the Infrastructure Improvements and the proposed form of bond as required by Section II, Infrastructure Improvements, Paragraph h), Permits and Performance Bonds (the “Performance Infrastructure Bond”), for completion of the Infrastructure Improvements to the City’s Department of Planning, Building and Development after submittal of the Infrastructure Improvements plans, if permits have been issued by the Department of Public Works.
3) Within four (4) weeks from receipt, the City shall review submissions of the Infrastructure Improvements plans, the application for right-of-way permits, proposed construction easements, and the Performance Infrastructure Bond and either issue permit and approval notification or notify the Developer of any deficiencies. This time period shall may be extended for any required review by any State the Michigan Department or Agencyof Environmental Quality. If deficiencies are noted, the Developer shall cure the deficiencies, and within two (2) weeks of the submission of any documentation to cure the deficiencies, the City shall advise the Developer of any deficiencies. Submission and review shall be repeated until no further deficiencies are noted.
4) The City shall grant construction easements to the Developer on the City’s standard forms, within 2 weeks of notification of approval of the plans.
5) Prior to the start of construction, the Developer shall submit the Performance Infrastructure Bond as required by Section II. The Developer shall begin construction of the Infrastructure Improvements within 4 weeks of issuance of permits and easements.
6) The Developer shall complete construction of the Infrastructure Improvements within 24 months of issuance of permits, and dedicate the Infrastructure Improvements and convey the utilities with required easements within 2 months thereafter.
Appears in 1 contract
Samples: Development Agreement
Infrastructure. 1) The Developer shall submit the Infrastructure Improvements plans and application for rightRight-of-way permits Way Permit to construct the Infrastructure Improvements to the City’s Department of Public Works along with proposed utility easements by May 1, 20192018.
2) The Developer shall submit proof reasonably satisfactory to the City of financing that is adequate to complete the Infrastructure Improvements financial assurances and the proposed form of bond as required by Section II, Infrastructure Improvements, Paragraph h)paragraph e, Permits and Performance Bonds (the “Performance Bond”), for completion of the Infrastructure Improvements to the City’s Department of Planning, Building and Development after submittal of the Infrastructure Improvements plans, if permits have been issued by the Department of Public Works.
3) Within four (4) weeks from receipt, the City shall review submissions of the Infrastructure Improvements plans, the application for rightRight-of-way permitsWay Permit, proposed construction easements, and the Performance Bond and either issue permit and approval notification or notify the Developer of any deficiencies. This time period shall may be extended for any required review by any State the Michigan Department or Agencyof Environmental Quality. If deficiencies are noted, the Developer shall cure the deficiencies, and within two (2) weeks of the submission of any documentation to cure the deficiencies, the City shall advise the Developer of any deficiencies. Submission and review shall be repeated until no further deficiencies are noted.
4) The City shall grant construction easements to the Developer on the City’s standard forms, within 2 weeks of notification of approval of the plans.
5) Prior to the start of construction, the Developer shall submit the Performance Bond as required by Section II. The Developer shall begin construction of the Infrastructure Improvements within 4 weeks of issuance of permits and easements, subject to the limitation that any demolition or construction activities on the DDA Evergreen Property cannot begin before May 9, 2018.
6) The Developer shall complete construction of the Infrastructure Improvements within 24 months of issuance of permits, and dedicate the Infrastructure Improvements and convey the utilities with required easements within 2 months thereafter.
Appears in 1 contract
Samples: Development Agreement
Infrastructure. 1) The Developer shall submit the Infrastructure Improvements plans and application for right-of-way permits to construct the Infrastructure Improvements to the City’s Department of Public Works along with proposed utility easements by May 1, 2019.
2) The Developer shall submit proof reasonably satisfactory to the City of financing that is adequate to complete the Infrastructure Improvements and the proposed form of bond as required by Section II, Infrastructure Improvements, Paragraph h), Permits and Performance Bonds (the “Infrastructure Performance Bond”), for completion of the Infrastructure Improvements to the City’s Department of Planning, Building and Development after submittal of the Infrastructure Improvements plans, if permits have been issued by the Department of Public Works.
3) Within four (4) weeks from receipt, the City shall review submissions of the Infrastructure Improvements plans, the application for right-of-way permits, proposed construction easements, and the Infrastructure Performance Bond and either issue permit and approval notification or notify the Developer of any deficiencies. This time period may shall be extended for any required review by any State the Michigan Department or Agency. If deficiencies are noted, the Developer shall cure the deficiencies, of Environmental Qualityany and within two (2) weeks of the submission of any documentation to cure the deficiencies, the City shall advise the Developer of any deficiencies. Submission and review shall be repeated until no further deficiencies are noted.
4) The City shall grant construction easements to the Developer on the City’s standard forms, within 2 weeks of notification of approval of the plans.
5) Prior to the start of construction, the Developer shall submit the Performance Bond as required by Section II. The Developer shall begin construction of the Infrastructure Infrastructure Improvements within 4 weeks of issuance of permits and easements.
6) The Developer shall complete construction of the Infrastructure Improvements within 24 months of issuance of permits, and dedicate the Infrastructure Improvements and convey the utilities with required easements within 2 months thereafter.
Appears in 1 contract
Samples: Development Agreement
Infrastructure. 1) The Developer shall submit the Infrastructure Improvements plans and application for rightRight-of-way permits Way Permit to construct the Infrastructure Improvements to the City’s Department of Public Works along with proposed utility easements by May 1, 20192018.
2) The Developer shall submit proof reasonably satisfactory to the City of financing that is adequate to complete the Infrastructure Improvements infrastructure improvements and the proposed form of bond as required by Section II, Infrastructure Improvements, Paragraph paragraph h), Permits and Performance Bonds (the “Performance Bond”), for completion of the Infrastructure Improvements to the City’s Department of Planning, Building and Development after submittal of the Infrastructure Improvements plans, if permits have been issued by the Department of Public Works.
3) Within four (4) weeks from receipt, the City shall review submissions of the Infrastructure Improvements plans, the application for rightRight-of-way permitsWay Permit, proposed construction easements, and the Performance Bond and either issue permit and approval notification or notify the Developer of any deficiencies. This time period shall may be extended for any required review by any State the Michigan Department or Agencyof Environmental Quality. If deficiencies are noted, the Developer shall cure the deficiencies, and within two (2) weeks of the submission of any documentation to cure the deficiencies, the City shall advise the Developer of any deficiencies. Submission and review shall be repeated until no further deficiencies are noted.
4) The City shall grant construction easements to the Developer on the City’s standard forms, within 2 weeks of notification of approval of the plans.
5) Prior to the start of construction, the Developer shall submit the Performance Bond as required by Section II. The Developer shall begin construction of the Infrastructure Improvements within 4 weeks of issuance of permits and easements, subject to the limitation that any demolition or construction activities on the DDA Evergreen Property cannot begin before August 9, 2018.
6) The Developer shall complete construction of the Infrastructure Improvements within 24 months of issuance of permits, and dedicate the Infrastructure Improvements and convey the utilities with required easements within 2 months thereafter.
Appears in 1 contract
Samples: Development Agreement
Infrastructure. 1i) The Developer shall submit the Infrastructure Improvements plans and specifications, and application for right-of-way permits to construct the Infrastructure Improvements to the City’s Department of Public Works along with proposed utility easements by May 1_, 201920 .
2ii) The Developer shall submit proof reasonably satisfactory to the City of financing that is adequate to complete the Infrastructure Improvements and the proposed form of bond as required by Section II, Infrastructure Improvements, Paragraph h), Permits and Performance Bonds (the “Performance Bond”), for completion of the Infrastructure Improvements to the City’s Department of Planning, Building and Development after submittal of the Infrastructure Improvements plans, if permits have been issued by the Department of Public Works.
3iii) Within four (4) weeks from receipt, the City shall review submissions of the Infrastructure Improvements plans, the application for right-of-way permits, proposed construction easements, and the Performance Bond and either issue permit and approval notification or notify the Developer of any deficiencies. This time period shall be extended for any required review by any State Department or Agency. If deficiencies are noted, the Developer shall cure the deficiencies, and within two (2) weeks of the submission of any documentation to cure the deficiencies, the City shall advise the Developer of any deficiencies. Submission and review shall be repeated until no further deficiencies are noted.
4iv) The City shall grant construction easements to the Developer on the City’s standard forms, within 2 weeks of notification of approval of the plans.
5v) Prior to the start of construction, the Developer shall submit the Performance Bond as required by Section II. The Developer shall begin construction of the Infrastructure Improvements within 4 weeks of issuance of permits and easements.
6vi) The Developer shall complete construction of the Infrastructure Improvements within 24 months of issuance of permits, and dedicate the Infrastructure Improvements and convey the utilities with required easements within 2 months thereafter.
Appears in 1 contract
Samples: Development Agreement