Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3. (ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them. (iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions. (iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 24 contracts
Sources: Engineering Procurement and Construction Agreement, Contract Agreement, Construction Contract
Instructions of the Authority’s Engineer. (i) 18.4.1 The Authority’s Engineer may issue to the Contractor instructions for remedying any Defect(s) to the ContractorDefect. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) 18.4.2 The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
(iii) 18.4.3 In case the Contractor does not receive the confirmation of the oral instructions instruction within the time specified in Clause 18.4 (ii)18.4.2, the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructionsinstruction.
(iv) 18.4.4 In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three) )] business days of the dispute being referred.
Appears in 22 contracts
Sources: Construction Contract, Epc Agreement, Engineering, Procurement & Construction (Epc) Agreement
Instructions of the Authority’s Engineer. (i) 18.4.1 The Authority’s Engineer may issue to the Contractor instructions for remedying any Defect(s) to the ContractorDefect. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) 18.4.2 The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
(iii) 18.4.3 In case the Contractor does not receive the confirmation of the oral instructions instruction within the time specified in Clause 18.4 (ii)18.4.2, the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructionsinstruction.
(iv) 18.4.4 In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 11 contracts
Sources: Draft Contract Agreement, Draft Contract Agreement (Dca), Contract Agreement
Instructions of the Authority’s Engineer.
(i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 10 contracts
Sources: Engineering Procurement and Construction (Epc) Contract, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing themissuingthem.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 7 contracts
Sources: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Instructions of the Authority’s Engineer. (i) 18.4.1 The Authority’s Authority‟s Engineer may issue to the Contractor instructions for remedying any Defect(s) to the ContractorDefect. The Contractor shall take such instructions from the Authority’s Authority‟s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) 18.4.2 The instructions issued by the Authority’s Authority‟s Engineer shall be in writing. However, if the Authority’s Authority‟s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
(iii) 18.4.3 In case the Contractor does not receive the confirmation of the oral instructions instruction within the time specified in Clause 18.4 (ii)18.4.2, the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Authority‟s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Authority‟s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Authority‟s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructionsinstruction.
(iv) 18.4.4 In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Authority‟s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three) )] business days of the dispute being referred.
Appears in 6 contracts
Sources: Engineering, Procurement and Construction Agreement, Construction Contract, Epc Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii18.4(ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement obtainacknowledgement from the Authority’s Engineer of the communication seeking written seekingwritten confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 5 contracts
Sources: Contract Agreement, Contract Agreement, Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii18.4(ii), the Contractor shall seek the written confirmation of the ofthe oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 5 contracts
Sources: Construction Contract, Contract Agreement, Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, Engineer or from an assistant to whom appropriate authority has been delegated under Clause 18.3Clause18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 5 contracts
Sources: Draft Contract Agreement, Construction Contract, Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause ▇▇▇▇▇▇ 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 3 contracts
Sources: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the ContractortheContractor. The Contractor shall take such instructions from the Authority’s Engineer, or Engineeror from an assistant to whom appropriate authority has been delegated under Clause 18.3Clause18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the ifthe Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm shallconfirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the withinthe time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of confirmationof the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement obtainacknowledgement from the Authority’s Engineer of the communication seeking written seekingwritten confirmation. In case of failure of the Authority’s Engineer or its delegated assistant delegatedassistant to reply to the Contractor within 2 (two) days of the receipt of the communication thecommunication from the Contractor, the Contractor may not carry out the instructionstheinstructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor theContractor may refer the dispute to the Authority’s Engineer, who shall then confirm, ,reverse or vary the instructions within 3 (three) business days of the dispute being referredbeingreferred.
Appears in 1 contract
Sources: Draft Contract Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation IncasetheContractordoesnotreceivetheconfirmationoftheoralinstructionswithin thetimespecifiedinClause18.4(ii),theContractorshallseekthewrittenconfirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Contract Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain Meghalaya Package II (Km 20.900 to Km 47.075 on EPC Mode through ADB Loan assistance acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Contract Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.. Page 92 of 144 floating material for providing floating Terminal facilities at various locations on NW – 2 (Brahmaputra River) on EPC mode Sept, 2021
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within IncasetheContractordoesnotreceivetheconfirmationoftheoralinstructionswithin the time specified in Clause 18.4 (ii18.4(ii), ; the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement an acknowledgment from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse reverse, or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Engineering Procurement and Construction (Epc) Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain Meghalaya Package III (Km 47.075 to Km 77.055) on EPC Mode through ADB Loan assistance acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Contract Agreement
Instructions of the Authority’s Engineer. (i) 18.4.1 The Authority’s Authority‟s Engineer may issue to the Contractor instructions for remedying any Defect(s) to the ContractorDefect. The Contractor shall take such instructions from the Authority’s Authority‟s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) 18.4.2 The instructions issued by the Authority’s Authority‟s Engineer shall be in writing. However, if the Authority’s Authority‟s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
(iii) 18.4.3 In case the Contractor does not receive the confirmation of the oral instructions instruction within the time specified in Clause 18.4 (ii)18.4.2, the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Authority‟s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Authority‟s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Authority‟s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructionsinstruction.
(iv) 18.4.4 In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Authority‟s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Draft Contract Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (iiIncasetheContractordoesnotreceivetheconfirmationoftheoralinstructionswithin thetimespecifiedinClause18.4(ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Contract Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain paved shoulder from design Km 0+000 to Km 36+635 (Design Length= 36.635 Km) (existing Km 112+000 to Km 151+060 of Old NH-62) under Bharatmala Pariyojana (Lot-1) Pkg-1B on EPC mode in the state of Meghalaya acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Contract Agreement
Instructions of the Authority’s Engineer. (i)
18.4.1 The Authority’s Engineer may issue to the Contractor instructions for remedying any Defect(s) to the ContractorDefect. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) 18.4.2 The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
(iii) 18.4.3 In case the Contractor does not receive the confirmation of the oral instructions instruction within the time specified in Clause 18.4 (ii)18.4.2, the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructionsinstruction.
(iv) 18.4.4 In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three) )] business days of the dispute being referred.
Appears in 1 contract
Sources: Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.. Construction of New Two-Lane Bridge (Parallel to existing Naranarayan Setu) with its approaches from Km 0+000 to Km 4+385 across River Brahmaputra on NH-17 at 81 Jogighopa in the State of Assam
Appears in 1 contract
Sources: Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s 's Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s 's Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s 's Engineer shall be in writing. However, if the Authority’s 's Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s 's Engineer. The Contractor shall obtain acknowledgement from the Authority’s 's Engineer of the communication seeking written confirmation. In case of failure of the Authority’s 's Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructions.
(iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s 's Engineer, who shall then confirm, reverse or vary the instructions within 3 (three) business days of the dispute being referred.
Appears in 1 contract
Sources: Construction Contract