Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3. (ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them. (iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain
Appears in 6 contracts
Samples: Construction Contract, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Instructions of the Authority’s Engineer. (i) 16.4.1 The Authority’s Engineer may issue to the Contractor instructions for remedying any Defect(s) to the ContractorDefect. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3Engineer only.
(ii) 16.4.2 The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
(iii) 16.4.3 In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii)16.4.2, the Contractor shall seek the written confirmation of the oral instructions from the Authority’s EngineerEngineer and shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. The In case of failure of the Authority’s Engineer to reply to the Contractor shall obtainwithin 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instruction.
Appears in 4 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii18.4(ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtainobtainacknowledgement from the Authority’s Engineer of the communication seekingwritten confirmation. In case of failure of the Authority’s Engineer or its
Appears in 3 contracts
Samples: Contract Agreement, Contract Agreement, Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing themissuingthem.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtainobtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated
Appears in 2 contracts
Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing themissuingthem.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain
Appears in 2 contracts
Samples: Contract Agreement, Construction Contract
Instructions of the Authority’s Engineer. (i) The Authority’s Engineer may issue instructions for remedying any Defect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
(ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm the oral instructions in writing within 2 (two) working days of issuing them.
(iii) In case the Contractor does not receive the confirmation of the oral instructions within the time specified in Clause 18.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtainconfirmation
Appears in 1 contract
Samples: Contract Agreement