Instructions of the Authority’s Engineer. 18.4.1 The Authority’s Engineer may issue to the Contractor instructions for remedying any Defect. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3. 18.4.2 The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions within 2 (two) working days of issuing them. 18.4.3 In case the Contractor does not receive the confirmation of the oral instruction within the time specified in Clause 18.4.2, the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instruction. 18.4.4 In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three)] business days of the dispute being referred.
Appears in 1 contract
Samples: And Construction Agreement
Instructions of the Authority’s Engineer. 18.4.1 (i) The Authority’s Engineer may issue to the Contractor instructions for remedying any DefectDefect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
18.4.2 . (ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
18.4.3 issuingthem. (iii) In case the Contractor does not receive the confirmation of the oral instruction instructions within the time specified in Clause 18.4.218.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain Draft Contract AgreementPage 97 of 261 S-D Tunnel 2022 acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instruction.
18.4.4 instructions. (iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three)] ) business days of the dispute being referred.. 18.5
Appears in 1 contract
Samples: nhidcl.com
Instructions of the Authority’s Engineer. 18.4.1 (i) The Authority’s Engineer may issue to the Contractor instructions for remedying any DefectDefect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
18.4.2 (ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
18.4.3 (iii) In case the Contractor does not receive the confirmation of the oral instruction instructions within the time specified in Clause 18.4.218.4(ii), the Contractor shall seek the written confirmation of the ofthe oral instructions from the Authority’s Engineer. The Contractor shall obtain acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instructioninstructions.
18.4.4 (iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three)] ) business days of the dispute being referred.
Appears in 1 contract
Samples: Draft Contract Agreement
Instructions of the Authority’s Engineer. 18.4.1 (i) The Authority’s Engineer may issue to the Contractor instructions for remedying any DefectDefect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
18.4.2 . (ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
18.4.3 issuingthem. (iii) In case the Contractor does not receive the confirmation of the oral instruction instructions within the time specified in Clause 18.4.218.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain Drafit Concession AgreementPage 96 of 145 Restoration & Rehabilitation of Road from Km 21.00 to Km 28.00 on NH-4 (old NH-233) in the Union Territory of Andaman & Nicobar Islands in the FY 2022-23 on EPC Basis Jun. 2022 acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instruction.
18.4.4 instructions. (iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three)] ) business days of the dispute being referred.. 18.5
Appears in 1 contract
Samples: Construction Agreement
Instructions of the Authority’s Engineer. 18.4.1 (i) The Authority’s Engineer may issue to the Contractor instructions for remedying any DefectDefect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
18.4.2 . (ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
18.4.3 issuingthem. (iii) In case the Contractor does not receive the confirmation of the oral instruction instructions within the time specified in Clause 18.4.218.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain Draft Contract AgreementPage 96 of 145 Aug. 2020 acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instruction.
18.4.4 instructions. (iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three)] ) business days of the dispute being referred.. 18.5
Appears in 1 contract
Samples: Draft Contract Agreement
Instructions of the Authority’s Engineer. 18.4.1 (i) The Authority’s Engineer may issue to the Contractor instructions for remedying any DefectDefect(s) to the Contractor. The Contractor shall take such instructions from the Authority’s Engineer, or from an assistant to whom appropriate authority has been delegated under Clause 18.3.
18.4.2 . (ii) The instructions issued by the Authority’s Engineer shall be in writing. However, if the Authority’s Engineer issues any oral instructions to the Contractor, it shall confirm in writing the oral instructions in writing within 2 (two) working days of issuing them.
18.4.3 issuingthem. (iii) In case the Contractor does not receive the confirmation of the oral instruction instructions within the time specified in Clause 18.4.218.4 (ii), the Contractor shall seek the written confirmation of the oral instructions from the Authority’s Engineer. The Contractor shall obtain Draft Contract AgreementPage 96 of 144 Construction of Uni-directional Tunnel i.e. length of 2.64/2.63km (Tube-1/Tube-2) and its approach (P-II) in the UT of J&K Jan. 2021 acknowledgement from the Authority’s Engineer of the communication seeking written confirmation. In case of failure of the Authority’s Engineer or its delegated assistant to reply to the Contractor within 2 (two) days of the receipt of the communication from the Contractor, the Contractor may not carry out the instruction.
18.4.4 instructions. (iv) In case of any dispute on any of the instructions issued by the delegated assistant, the Contractor may refer the dispute to the Authority’s Engineer, who shall then confirm, reverse or vary the instructions within [3 (three)] ) business days of the dispute being referred.. 18.5
Appears in 1 contract
Samples: Draft Contract Agreement