Common use of Interconnection System Impact Study Agreement Clause in Contracts

Interconnection System Impact Study Agreement. ‌ Unless otherwise agreed, pursuant to the Scoping Meeting provided in Section 3.3.4, simultaneously with the delivery of the Interconnection Feasibility Study to Interconnection Customer, Transmission Provider shall provide to Interconnection Customer an Interconnection System Impact Study Agreement in the form of Appendix 3 to this LGIP. The Interconnection System Impact Study Agreement shall provide that Interconnection Customer shall compensate Transmission Provider for the actual cost of the Interconnection System Impact Study. Transmission Provider shall use Reasonable Efforts to provide to Interconnection Customer a non-binding good faith estimate of the cost and timeframe for completing the Interconnection System Impact Study within three (3) Business Days following the Interconnection Feasibility Study results meeting.

Appears in 3 contracts

Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

AutoNDA by SimpleDocs

Interconnection System Impact Study Agreement. ‌ Unless otherwise agreed, pursuant to the Scoping Meeting provided in Section 3.3.43.4.4, simultaneously with the delivery of the Interconnection Feasibility Study to Interconnection Customer, Transmission Provider shall provide to Interconnection Customer an Interconnection System Impact Study Agreement in the form of Appendix 3 to this LGIP. The Interconnection System Impact Study Agreement shall provide that Interconnection Customer shall compensate Transmission Provider for the actual cost of the Interconnection System Impact Study. Transmission Provider shall use Reasonable Efforts to provide to Interconnection Customer a non-binding good faith estimate of the cost and timeframe for completing the Interconnection System Impact Study within three (3) Business Days following the Interconnection Feasibility Study results meeting.

Appears in 2 contracts

Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

AutoNDA by SimpleDocs

Interconnection System Impact Study Agreement. Unless otherwise agreed, pursuant to the Scoping Meeting provided in Section 3.3.4, simultaneously with the delivery of the Interconnection Feasibility Study to Interconnection Customer, Transmission Provider shall provide to Interconnection Customer an Interconnection System Impact Study Agreement in the form of Appendix 3 to this LGIP. The Interconnection System Impact Study Agreement shall provide that Interconnection Customer shall compensate Transmission Provider for the actual cost of the Interconnection System Impact Study. Transmission Provider shall use Reasonable Efforts to provide to Interconnection Customer a non-binding good faith estimate of the cost and timeframe for completing the Interconnection System Impact Study within three (3) Business Days following the Interconnection Feasibility Study results meeting.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)