Interfacing. (1) The Construction Manager shall take such measures as- appropriate to provide that construction requirements will be covered in the separate sub-contracts for procurement of long lead items, the separate construction sub-contracts and the general conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work included in that particular separate sub- contract, its schedule for start and completion and its relationship to other separate Construction Managers. Without assuming any Design responsibilities of the Architect-Engineer, the Construction Manager shall include in the reports required under Article 2.2.1 comments on overlap with any other separate sub- contracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager and Architect-Engineer may arrange for necessary corrections.
Appears in 10 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Interfacing. (1a) The Construction Manager shall take such measures as- as are appropriate to provide that all construction requirements will be covered in the separate sub-contracts subcontracts for procurement of long lead items, the separate construction sub-contracts subcontracts and the general conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work included in that particular separate sub- contractsubcontract, its schedule for start and completion and its relationship to other separate Construction Managers. contractors.
(b) Without assuming any Design responsibilities of the Architect-Engineer, the Construction Manager shall include in the reports required under Article 2.2.1 2.2(3), comments on overlap with any other separate sub- contractssubcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager Owner and Architect-Engineer may arrange for necessary corrections.
Appears in 6 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement, Construction Manager Agreement
Interfacing. (1a) The Construction Manager shall take such measures as- as are appropriate to provide that all construction requirements will be covered in the separate sub-contracts subcontracts for procurement of long lead items, the separate construction sub-contracts subcontracts and the general conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work included in that particular separate sub- contractsubcontract, its schedule for start and completion and its relationship to other separate Construction Managers. .
(b) Without assuming any Design responsibilities of the Architect-Engineer, the Construction Manager shall include in the reports required under Article 2.2.1 2.3(2) comments on overlap with any other separate sub- contractssubcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager Director and Architect-Engineer may arrange for necessary corrections.
Appears in 2 contracts
Samples: Construction Project Agreement, Construction Project Agreement
Interfacing. (1) A. The Construction Manager shall take such measures as- as are appropriate to provide that all construction requirements will be covered in the separate sub-contracts subcontracts for procurement of long lead items, the separate construction sub-contracts subcontracts and the general conditions General Conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work included in that particular separate sub- contractsubcontract, its schedule for start and completion and its relationship to other separate Construction Managers. contractors.
B. Without assuming any Design design responsibilities of the Architect-EngineerArchitect‑Engineer, the Construction Manager shall include in the reports required under Article 2.2.1 2.3(4) comments on overlap with any other separate sub- contractssubcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager Owner and Architect-Engineer Architect‑Engineer may arrange for necessary corrections.
Appears in 1 contract
Samples: Construction Manager Agreement
Interfacing. (1a) The Construction Manager shall take such measures as- as are appropriate to provide that all construction requirements will be covered in the separate sub-contracts subcontracts for procurement of long lead items, the separate construction sub-contracts subcontracts and the general conditions items performed without duplication or overlap, and that subcontracts are sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work Work included in that particular separate sub- contract, subcontract; its schedule for start and completion and its relationship to other separate Construction Managers. .
(b) Without assuming any Design responsibilities of the Architect-Engineer, the Construction Manager shall include in the any reports required under Article 2.2.1 2.3(2) comments on identified overlap with any other separate sub- contractssubcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager of Facilities Planning and Architect-Engineer may arrange for necessary corrections.
Appears in 1 contract
Samples: Building Construction Agreement
Interfacing. (1a) The Construction Manager shall take such measures as- as are appropriate to provide that all construction requirements will be covered in the separate sub-contracts subcontracts for procurement of long lead items, the separate construction sub-contracts subcontracts and the general conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work Work included in that particular separate sub- contract, subcontract; its schedule for start and completion and its relationship to other separate Construction Managers. .
(b) Without assuming any Design responsibilities of the Architect-Engineer, the Construction Manager shall include in the any reports required under Article 2.2.1 2.3(2) comments on identified overlap with any other separate sub- contractssubcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager of Facilities Planning and Architect-Engineer Architect -Engineer may arrange for necessary corrections.
Appears in 1 contract
Samples: Building Construction Agreement
Interfacing. (1a) The Construction Manager shall take such measures as- as are appropriate to provide that all construction requirements will be covered in the separate sub-contracts subcontracts for procurement of long lead items, the separate construction sub-contracts subcontracts and the general conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work included in that particular separate sub- contractsubcontract, its schedule for start and completion and its relationship to other separate Construction Managers. subcontractors.
(b) Without assuming any Design design responsibilities of the Architect-Engineer, the Construction Manager shall include in the reports required under Article 2.2.1 2.3(2) comments on overlap with any other separate sub- contractssubcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager and Architect-Engineer may arrange for necessary corrections.
Appears in 1 contract
Samples: Construction Manager Agreement
Interfacing. (1a) The Construction Manager shall take such measures as- as are appropriate to provide that all construction requirements will be covered in the separate sub-contracts subcontracts for procurement of long lead items, the separate construction sub-contracts subcontracts and the general conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work Work included in that particular separate sub- contract, subcontract; its schedule for start and completion and its relationship to other separate Construction Managers. .
(b) Without assuming any Design responsibilities of the Architect-Engineer, the Construction Manager shall include in the any reports required under Article 2.2.1 2.3(2) comments on identified overlap with any other separate sub- contractssubcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Project Manager of Facilities Planning and Architect-Engineer may arrange for necessary corrections.
Appears in 1 contract
Samples: Building Construction Agreement