Layout Responsibility. Contractor or Owner shall establish principal axis lines and levels, and control points, whereupon Subcontractor shall be strictly responsible for the layout and accuracy of its Subcontract Work in accordance with the locations, lines and grades specified or shown in the Contract Documents, subject to such modifications as Contractor may require as the Subcontract Work progresses. Subcontractor is responsible for any loss or damages to other subcontractors engaged in work on the site by reason of failure of Subcontractor to set out or perform its work correctly. Subcontractor is responsible for the layout of all points and grades in excess of building corners, column lines, grid lines and finish floor elevations (which will be established by Contractor). Subcontractor shall exercise prudence so that actual final conditions and details shall result in alignment of finish surfaces that are within industry standard tolerances. If Subcontractor moves or destroys or renders inaccurate any survey control point, such control point shall be replaced by Contractor at Subcontractor’s expense.
Appears in 13 contracts
Samples: Subcontract Agreement, Subcontract Agreement, Subcontract Agreement
Layout Responsibility. Contractor, General Contractor or Owner shall establish principal axis lines and levels, and control points, whereupon Subcontractor shall be strictly responsible for the layout and accuracy of its Subcontract Work in accordance with the locations, lines and grades specified or shown in the Contract Documents, subject to such modifications as Contractor may require as the Subcontract Work progresses. Subcontractor is responsible for any loss or damages to other subcontractors persons or entities engaged in work on the site by reason of failure of Subcontractor to set out or perform its work correctly. Subcontractor is responsible for the layout of all points and grades in excess of building corners, column lines, grid lines and finish floor elevations (which will be established by Contractor). Subcontractor shall exercise prudence so that actual final conditions and details shall result in alignment of finish surfaces that are within industry standard tolerances. If Subcontractor moves or destroys or renders inaccurate any survey control point, such control point shall be replaced by Contractor at Subcontractor’s expense.
Appears in 7 contracts
Samples: Subcontract Agreement, Subcontract Agreement, Subcontract Agreement
Layout Responsibility. Contractor or Owner shall establish principal axis lines and levels, and control points, whereupon Subcontractor shall be strictly responsible for the layout and accuracy of its Subcontract Work in accordance with the locations, lines and grades specified or shown in the Contract Documents, subject to such modifications as Contractor may require as the Subcontract Work progresses. Subcontractor is responsible for any loss or damages to other subcontractors engaged in work on the site by reason of failure of Subcontractor to set out or perform its work correctly. Subcontractor is responsible for the layout of all points and grades in excess of building corners, column lines, grid lines and finish floor elevations (which will be established by Contractor). Subcontractor shall exercise prudence so that actual final conditions and details shall result in alignment of finish surfaces that are within industry standard tolerances. If Subcontractor moves or destroys or renders inaccurate any survey control point, such control point shall be replaced by Contractor at Subcontractor’s 's expense.
Appears in 6 contracts
Samples: Subcontract Agreement, Subcontract Agreement, Subcontract Agreement
Layout Responsibility. Contractor, General Contractor or Owner shall establish principal axis lines and levels, and control points, whereupon Subcontractor shall be strictly responsible for the layout and accuracy of its Subcontract Work in accordance with the locations, lines and grades specified or shown in the Contract Documents, subject to such modifications as Contractor may require as the Subcontract Work progresses. Subcontractor is responsible for any loss or damages to other subcontractors contractors engaged in work on the site by reason of failure of Subcontractor to set out or perform its work correctly. Subcontractor is responsible for the layout of all points and grades in excess of building corners, column lines, grid lines and finish floor elevations (which will be established by Contractor). Subcontractor shall exercise prudence so that actual final conditions and details shall result in alignment of finish surfaces that are within industry standard tolerances. If Subcontractor moves or destroys or renders inaccurate any survey control point, such control point shall be replaced by Contractor at Subcontractor’s expense.
Appears in 2 contracts
Samples: Sub Subcontract Agreement, Sub Subcontract Agreement
Layout Responsibility. Contractor, General Contractor or Owner shall establish principal axis lines and levels, and control points, whereupon Subcontractor shall be strictly responsible for the layout and accuracy of its Subcontract Work in accordance with the locations, lines and grades specified or shown in the Contract Documents, subject to such modifications as Contractor may require as the Subcontract Work progresses. Subcontractor is responsible for any loss or damages to other subcontractors contractors engaged in work on the site by reason of failure of Subcontractor to set out or perform its work correctly. Subcontractor is responsible for the layout of all points and grades in excess of building corners, column lines, grid lines and finish floor elevations (which will be established by Contractor). Subcontractor shall exercise prudence so that actual final conditions and details shall result in alignment of finish surfaces that are within industry standard tolerances. If Subcontractor moves or destroys or renders inaccurate any survey control point, such control point shall be replaced by Contractor at Subcontractor’s 's expense.
Appears in 1 contract
Samples: Sub Subcontract Agreement
Layout Responsibility. Contractor, General Contractor or Owner shall establish principal axis lines and levels, and control points, whereupon Subcontractor shall be strictly responsible for the layout and accuracy of its Subcontract Work in accordance with the locations, lines and grades specified or shown in the Contract Documents, subject to such modifications as Contractor may require as the Subcontract Work progresses. Subcontractor is responsible for any loss or damages to other subcontractors persons or entities engaged in work on the site by reason of failure of Subcontractor to set out or perform its work correctly. Subcontractor is responsible for the layout of all points and grades in excess of building corners, column lines, grid lines and finish floor elevations (which will be established by Contractor). Subcontractor shall exercise prudence so that actual final conditions and details shall result in alignment of finish surfaces that are within industry standard tolerances. If Subcontractor moves or destroys or renders inaccurate any survey control point, such control point shall be replaced by Contractor at Subcontractor’s expense.. SAMPLE
Appears in 1 contract
Samples: Subcontract Agreement