Limitation on Contract Time Extensions. Any extension of the Contract Time allowed hereunder shall exclude any delay to the extent that it: (a) Did not impact the Critical Path affecting the Contract Time; (b) Was due to the fault or negligence, or act or failure to act of any Contractor- Related Entity; (c) Could reasonably have been avoided by Contractor, including by re- sequencing, reallocating or redeploying its forces to other portions of the Work (provided that if the request for extension involves an Owner caused delay, Owner shall have agreed, if requested to do so, to reimburse Contractor for its costs incurred, if any, in re-sequencing, reallocating, or redeploying its forces); or (d) Was concurrent with any other delay for which Contractor is not entitled to an extension of the Contract Time. Contractor shall be required to demonstrate to Owner’s satisfaction that the change in the Work or other event or situation that is the subject of a Change Order seeking a change in the Contract Time has caused or will result in an identifiable and measurable Delay which has impacted the Critical Path activity affecting the Contract Time.
Appears in 2 contracts
Samples: General Provisions Agreement, California High Speed Train Project Agreement
Limitation on Contract Time Extensions. Any extension of the Contract Time allowed hereunder shall exclude any delay to the extent that it:
(a) a. Did not impact the Critical Path affecting the Contract Time;
(b) b. Was due to the fault or negligence, or act or failure to act of any Contractor- Related Entity;
(c) c. Could reasonably have been avoided by Contractor, including by re- sequencing, reallocating or redeploying its forces to other portions of the Work (provided that if the request for extension involves an Owner caused delay, Owner shall have agreed, if requested to do so, to reimburse Contractor for its costs incurred, if any, in re-sequencing, reallocating, or redeploying its forces); or
(d) d. Was concurrent with any other delay for which Contractor is not entitled to an extension of the Contract Time. Contractor shall be required to demonstrate to Owner’s satisfaction that the change in the Work or other event or situation that is the subject of a Change Order seeking a change in the Contract Time has caused or will result in an identifiable and measurable Delay which has impacted the Critical Path activity affecting the Contract Time.
Appears in 1 contract
Samples: General Provisions Agreement
Limitation on Contract Time Extensions. Any extension of the Contract Time allowed hereunder shall exclude any delay to the extent that it:
(a) Did not impact the Critical Path affecting the Contract Timea Trainset Acceptance Deadline;
(b) Was due to the fault or negligence, or act or failure to act of any Contractor- Related Entity;
(c) Could reasonably have been avoided by Contractor, including by re- sequencing, reallocating or redeploying its forces to other portions of the Work (provided that if the request for extension involves an Owner caused delayAuthority Delay, Owner Authority shall have agreed, if requested to do so, to reimburse Contractor for its costs incurred, if any, in re-sequencing, reallocating, or redeploying its forces); or
(d) Was concurrent with any other delay for which Contractor is not entitled to an extension of the Contract Time. Contractor shall be required to demonstrate to OwnerAuthority’s satisfaction that the change in the Work or other event or situation that is the subject of a Change Order seeking a change in the Contract Time has caused or will result in an identifiable and measurable Delay which has impacted the Critical Path activity affecting the Contract Time.
Appears in 1 contract
Samples: Trainset Agreement