Master Plan. 5.11.1 The Concessionaire shall no later than 90 (ninety) days of the Appointed Date, prepare and submit, for review and comments from the Independent Engineer/ authorised representative of the Authority, a draft master plan ("Master Plan") for the Project. The Master Plan shall include, but not be limited to, the following: (a) zoning and allocation of the areas for different Emergency Services, OPD Services, Inpatient Services, and Diagnostics Services for various phases of development; (b) planning and lay out of the infrastructure required for the Site, including: (i) roads and storm drainage; (ii) common utilities like street lighting; (iii) waste management and effluent treatment plant, sewage network; (iv) car, two-▇▇▇▇▇▇▇ and cycle parking area; (v) area identified for installation of power back-up equipment; (vi) storage area; (vii) any other facilities necessary for and/or ancillary to a modern hospital. (c) Specialties and multi specialties to be provided in the Hospital with bed allocation plan within new hospital; (d) details of all medical and clinical facilities and services to be provided in the Hospital including Pharmacy, intensive care, ambulatory care services and other such medicinal and clinical facilities; (e) details of support Healthcare Services, facilities and utilities to be provided including diagnostics, mortuary, administration/back office and cafeteria; (f) medical waste disposal and treatment facilities; (g) detailed project milestones during construction phase for quarterly monitoring of the progress. In addition to the above, the Concessionaire is required to provide the details of medical and non-medical equipment or any further information as may be reasonably required by the Authority. 5.11.2 On receipt of the Master Plan, the Independent Engineer/ authorised representative of the Authority shall review the Master Plan submitted by the Concessionaire and provide its comments/observations and suggestions on the same within 30 (thirty) days from the date of the receipt of such Master Plan by the Independent Engineer/ authorised representative of the Authority. Upon receipt of such comments/observations and suggestions from the Independent Engineer/ authorised representative of the Authority, the Concessionaire shall submit the revised Master Plan to the Independent Engineer/ authorised representative of the Authority and the Independent Engineer/ authorised representative of the Authority shall submit the same for the approval of the Authority. 5.11.3 Upon receipt of the such Master Plan, the Authority in its capacity as the Special Planning Authority, shall review the said Master Plan and grant approval to the same with such modifications, as deemed fit to the Authority as per the provisions of the Applicable Laws and shall intimate the same to the Concessionaire. It is further agreed that no grant of approval by the Authority shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever {This Clause shall be applicable in the event NMPA is acting in the capacity of Special Planning Authority, otherwise such approvals shall be sought by the Concessionaire from relevant the local development bodies in accordance with Applicable Laws}. 5.11.4 The Concessionaire shall not be entitled to any extension of time for developing the Project or any other relief on account of delay caused due to providing any clarification or in resubmitting the Master Plan. 5.11.5 Notwithstanding the review by the Authority, the Concessionaire shall be solely responsible for any defect and/or deficiency in the Master Plan relating to the Project or any part thereof and accordingly the Concessionaire shall at all times remain responsible for its obligations under this Agreement. 5.11.6 The Concessionaire shall in no way represent to any person that, as a result of any review by the Authority, the Authority have accepted responsibility for the technical or soundness of any work relating to the Project or part thereof carried out by the Concessionaire and the Concessionaire shall, in accordance with the provisions of this Agreement, be solely responsible for the technical feasibility, operational capability and reliability of the Project or any part thereof.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Master Plan. 5.11.1 The Concessionaire shall no later than 90 (ninety) days of the Appointed Date, prepare and submit, for review and comments from the Independent Engineer/ authorised representative of the Authority, a draft master plan ("Master Plan") for the Project. The Master Plan shall include, but not be limited to, the following:
(a) zoning and allocation of the areas for different Emergency Services, OPD Services, Inpatient Services, and Diagnostics Services for various phases of development;
(b) planning and lay out of the infrastructure required for the Site, including:
(i) roads and storm drainage;
(ii) common utilities like street lighting;
(iii) waste management and effluent treatment plant, sewage network;
(iv) car, two-▇▇▇▇▇▇▇ and cycle parking area;
(v) area identified for installation of power back-up equipment;
(vi) storage area;
(vii) any other facilities necessary for and/or ancillary to a modern hospital.
(c) Specialties and multi super specialties to be provided in the Hospital with bed allocation plan within new hospitalthe Hospital;
(d) details of all medical and clinical facilities and services to be provided in the Hospital including PharmacyHospital, intensive care, ambulatory care services and other such medicinal and clinical facilities;
(e) details of support Healthcare Services, facilities and utilities to be provided including diagnostics, mortuary, administration/back office and cafeteria;
(f) medical waste disposal and treatment facilities;
(g) detailed project milestones during construction development phase for quarterly monitoring of the progress. In addition to the above, the Concessionaire is required to provide the details of medical and non-medical equipment or any further information as may be reasonably required by the Authority.
5.11.2 On receipt of the Master Plan, the Independent Engineer/ authorised representative of the Authority shall review the Master Plan submitted by the Concessionaire and provide its comments/observations and suggestions on the same within 30 (thirty) days from the date of the receipt of such Master Plan by the Independent Engineer/ authorised representative of the Authority. Upon receipt of such comments/observations and suggestions from the Independent Engineer/ authorised representative of the Authority, the Concessionaire shall submit the revised Master Plan to the Independent Engineer/ authorised representative of the Authority and the Independent Engineer/ authorised representative of the Authority shall submit the same for the approval of the Authority.
5.11.3 Upon receipt of the such Master Plan, the Authority in its capacity as the Special Planning Authority, shall review the said Master Plan and grant approval to the same with such modifications, as deemed fit to the Authority as per the provisions of the Applicable Laws and shall intimate the same to the Concessionaire. It is further agreed that no grant of approval by the Authority shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever {This whatsoever{This Clause shall be applicable in the event NMPA is VOCPAis acting in the capacity of Special Planning Authority, otherwise such approvals shall be sought by the Concessionaire from relevant the local development bodies in accordance with Applicable Laws}.
5.11.4 The Concessionaire shall not be entitled to any extension of time for developing the Project or any other relief on account of delay caused due to providing any clarification or in resubmitting the Master Plan.
5.11.5 Notwithstanding the review by the Authority, the Concessionaire shall be solely responsible for any defect and/or deficiency in the Master Plan relating to the Project or any part thereof and accordingly the Concessionaire shall at all times remain responsible for its obligations under this Agreement.
5.11.6 The Concessionaire shall in no way represent to any person that, as a result of any review by the Authority, the Authority have accepted responsibility for the technical or soundness of any work relating to the Project or part thereof carried out by the Concessionaire and the Concessionaire shall, in accordance with the provisions of this Agreement, be solely responsible for the technical feasibility, operational capability and reliability of the Project or any part thereof.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Master Plan. 5.11.1 5.12.1 The Concessionaire shall no later than 90 (ninety) days of the Appointed Date, prepare and submit, for review and comments from the Independent Engineer/ authorised representative of the Authority, Authority a draft master plan ("Master Plan") for the Project. The Master Plan shall include, but not be limited to, the following:
(a) zoning and allocation of the areas for different Emergency Services, OPD Services, Inpatient Services, and Diagnostics Services for various phases of development;
(b) planning and lay out of the infrastructure required for the Site, includingincluding :
(i) roads and storm drainage;
(ii) common utilities like street lighting;
(iii) waste management and effluent treatment plant, sewage network;
(iv) car, two-▇▇▇▇▇▇▇ and cycle parking area;
(v) area identified for installation of power back-up equipment;
(vi) storage area;
(vii) any other facilities necessary for and/or ancillary to a modern hospital.
(c) Specialties and multi super specialties to be provided in the Hospital with bed allocation plan within new hospitalplan;
(d) details of all medical and clinical facilities and services to be provided in the Hospital including Pharmacy, intensive care, ambulatory care services and other such medicinal and clinical facilities;
(e) details of support Healthcare Services, facilities and utilities to be provided including diagnostics, mortuary, administration/back office office, pharmacy and cafeteria;
(f) medical waste disposal and treatment facilities;
(g) detailed project milestones during construction phase for quarterly monitoring of the progress. progress In addition to the above, the Concessionaire is required to provide the details of medical and non-medical equipment or any further information as may be reasonably required by the Authority.
5.11.2 5.12.2 On receipt of the Master Plan, the Independent Engineer/ authorised representative of the Authority shall review the Master Plan submitted by the Concessionaire and provide its comments/observations and suggestions on the same within 30 (thirty) days from the date of the receipt of such Master Plan by the Independent Engineer/ authorised representative of the Authority. Upon receipt of such comments/observations and suggestions from the Independent Engineer/ authorised representative of the Authority, the Concessionaire shall will submit the revised Master Plan to the Independent Engineer/ authorised representative of the Authority and the Independent Engineer/ authorised representative of the Authority shall submit the same for the approval of the Authority.
5.11.3 5.12.3 Upon receipt of the such Master Plan, the Authority in its capacity as the Special Planning Authority, shall review the said Master Plan and grant approval to the same with such modifications, as deemed fit to the Authority as per the provisions of the Applicable Laws and shall intimate the same to the Concessionaireconcessionaire. It is further agreed that no grant of approval by the Authority shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever {This Clause shall be applicable in the event NMPA is acting in the capacity of Special Planning Authority, otherwise such approvals shall be sought by the Concessionaire from relevant the local development bodies in accordance with Applicable Laws}whatsoever.
5.11.4 5.12.4 The Concessionaire shall not be entitled to any extension of time for developing the Project or any other relief on account of delay caused due to providing any clarification or in resubmitting the Master Plan.
5.11.5 5.12.5 Notwithstanding the review by the Authority, the Concessionaire shall be solely responsible for any defect and/or deficiency in the Master Plan relating to the Project or any part thereof and accordingly the Concessionaire shall at all times remain responsible for its obligations under this Agreement.
5.11.6 5.12.6 The Concessionaire shall in no way represent to any person that, as a result of any review by the Authority, the Authority have accepted responsibility for the technical or soundness of any work relating to the Project or part thereof carried out by the Concessionaire and the Concessionaire shall, in accordance with the provisions of this Agreement, be solely responsible for the technical feasibility, operational capability and reliability of the Project or any part thereof.
Appears in 1 contract
Sources: Concession Agreement