Modification of Contract Time. Contract Time can only be adjusted by duly executed Change Order proposed, prepared, and executed in accordance with this Article and Article VIII. Neither Design-Builder’s submittal of a proposed schedule revision, nor the ADR’s review of one, changes the then-current Project Schedule – nor do they modify Design-Builder’s obligations under this Agreement.
Appears in 3 contracts
Samples: Standard Form of Agreement, Design Build Agreement, Construction Contract
Modification of Contract Time. Contract Time can only be adjusted by duly executed Change Order proposed, prepared, and executed in accordance with this Article and Article VIII. Neither Design-BuilderContractor’s submittal of a proposed schedule revision, nor the ADR’s review of one, changes the then-current Project Schedule – nor do they modify Design-BuilderContractor’s obligations under this Agreement.