Monitoring the Work. The Engineer will monitor the work regularly to identify any deviations from the Contractor’s scheduled performance relative to the currently accepted Baseline or Revised Progress Schedule. The Engineer may request a meeting with the Contractor to discuss the Contractor’s current progress or to establish the approximate date for starting each critical inspection stage. At least once a week, the Contractor shall advise the Engineer of the approximate timing for anticipated critical stages for the subsequent week. The Engineer shall be advised at least 24 hours in advance of any changes in planned operations or critical path. The cost of the Two Week Look Ahead schedules and Progress Meetings shall be included in the Contractor’s bid.
Appears in 28 contracts
Samples: sheriff.loudoun.gov, www.loudoun.gov, www.loudoun.gov