Common use of Monthly Progress Reports Clause in Contracts

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 7 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement

AutoNDA by SimpleDocs

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Authority‟s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Authority‟s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 7 contracts

Samples: Engineering, Procurement and Construction Agreement, Epc Agreement, Construction Contract

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Authority Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents AuthorityEngineeralong with all resources deployed and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14all problems faced during work.

Appears in 6 contracts

Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Employer and the Authority’s Employer's Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Employer's Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 3 contracts

Samples: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents Engineer along with all resources deployed and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14all problems faced during work.

Appears in 3 contracts

Samples: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports Contractor agrees that reporting under this Clause 11.7 shall include safety statistics, including details continue until the date of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.the completion of the Works. Each report shall include:

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Employer and the AuthorityEmployer’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the AuthorityEmployer’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 2 contracts

Samples: Epc Agreement, Contract Agreement for Design and Construction

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports Contractor agrees that reporting under this Clause 11.7 shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.continue until the

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports Contractor agrees that reporting under this Clause 11.7 shall include safety statistics, including details continue until the date of any hazardous incidents the completion of the Works. Each report shall include: Improvement and activities relating widening to environmental, resettlement and other obligations under Clauses 3.10 two lane with paved shoulder of road from Km 21.100 to 3.14.Km

Appears in 1 contract

Samples: Contract Agreement

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report re- port on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 1 contract

Samples: Construction Contract

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 1 contract

Samples: Engineering, Procurement and Construction (Epc) Agreement

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Authority/GMDA and the Authority’s AUTHORITY’S/GMDAs Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s AUTHORITY’S/GMDAs Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Employer and the Authority’s Employer‟s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Employer‟s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.

Appears in 1 contract

Samples: Epc Agreement