Common use of Monthly progressreports Clause in Contracts

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: (a) an executivesummary; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; (c) details of work subcontracted and the performance ofSub-contractors; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; (e) records of manpower and Contractor's equipment on theSite; (f) copies for that month of quality assurance documents, test results and certificates; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; (i) details of any unresolved disputes or claims, in relation to theProject; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; (l) details of various royalty payment and insurances required to be taken by the Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. (n) details of defects by theAuthority; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; (p) any Material AdverseEffect; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; (r) declaration specifying compliance with all Manuals provided to the Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 7 contracts

Samples: Contract Agreement, Contract Agreement, Engineering Procurement and Construction Agreement

AutoNDA by SimpleDocs

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: (a) an executivesummary; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; (c) details of work subcontracted and the performance ofSub-contractors; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; (e) records of manpower and Contractor's equipment on theSite; (f) copies for that month of quality assurance documents, test results and certificates; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; (i) details of any unresolved disputes or claims, in relation to theProject; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; (l) details of various royalty payment and insurances required to be taken by the Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. (n) details of defects by theAuthority; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; (p) any Material AdverseEffect; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; (r) declaration specifying compliance with all Manuals provided to the Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Construction Contract

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: : Draft Contract AgreementPage 71 of 146 “Construction of two lane with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Manipur from km 43.480 near Phelong Village to km 54.180 near Azuram Village (Length- 10.700 km) (Package-4) on EPC mode.” May 2021 (a) an executivesummary; ; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; ; (c) details of work subcontracted and the performance ofSub-contractors; ; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; ; (e) records of manpower and Contractor's equipment on theSite; ; (f) copies for that month of quality assurance documents, test results and certificates; ; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; ; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; ; (i) details of any unresolved disputes or claims, in relation to theProject; ; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; ; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; ; (l) details of various royalty payment and insurances required to be taken by the Contractor;and Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. . (n) details of defects by theAuthority; ; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; ; (p) any Material AdverseEffect; ; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; ; (r) declaration specifying compliance with all Manuals provided to the Contractor;and Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Construction Contract

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: (a) an executivesummary; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; (c) details of work subcontracted and the performance ofSub-contractors; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; (e) records of manpower and Contractor's equipment on theSite; (f) copies for that month of quality assurance documents, test results and certificates; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; (i) details of any unresolved disputes or claims, in relation to theProject; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; (l) details of various royalty payment and insurances required to be taken by the Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. (n) details of defects by theAuthority; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; (p) any Material AdverseEffect; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; (r) declaration specifying compliance with all Manuals provided to the Contractor;and (s) any change in the flow of traffic in the existing ProjectHighwayProject.

Appears in 1 contract

Samples: Construction Contract

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. Page 75 of 159 The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: (a) an executivesummary; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; (c) details of work subcontracted and the performance ofSub-contractors; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; (e) records of manpower and Contractor's equipment on theSite; (f) copies for that month of quality assurance documents, test results and certificates; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; (i) details of any unresolved disputes or claims, in relation to theProject; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; (l) details of various royalty payment and insurances required to be taken by the Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. (n) details of defects by theAuthority; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; (p) any Material AdverseEffect; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; (r) declaration specifying compliance with all Manuals provided to the Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Contract Agreement

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: (a) an executivesummary; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; (c) details of work subcontracted and the performance ofSub-contractors; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; (e) records of manpower and Contractor's equipment on theSite; (f) copies for that month of quality assurance documents, test results and certificates; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; (i) details of any unresolved disputes or claims, in relation to theProject; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; (l) details of various royalty payment and insurances required to be taken by the Contractor;and (m) such Such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. (n) details of defects by theAuthority; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; (p) any Material AdverseEffect; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; (r) declaration specifying compliance with all Manuals provided to the Contractor;and (s) any Any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Agreement

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the State of Manipur” November 2020 date of the completion of the Works. Each report shall include: (a) an executivesummary; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; (c) details of work subcontracted and the performance ofSub-contractors; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; (e) records of manpower and Contractor's equipment on theSite; (f) copies for that month of quality assurance documents, test results and certificates; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; (i) details of any unresolved disputes or claims, in relation to theProject; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; (l) details of various royalty payment and insurances required to be taken by the Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. (n) details of defects by theAuthority; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; (p) any Material AdverseEffect; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; (r) declaration specifying compliance with all Manuals provided to the Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Contract Agreement

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the Contract AgreementPage 75 of 154 “Construction of Four Lane Panchgram Bypass from Design Chainage km 15+500 on NH- 37 (Old NH-53) at Kalinagar Pt.-II Village to Design Chainage km 27+300 at crossing with NH-6 (Old NH-44) Near Xxxxxxxxx Pt.-I Village in the State of Assam on EPC Mode under Xxxxxxxxxx Xxxxxxxxxx in Economic Corridors (Project Length – 11.8 km)” (4th Call) Mar 2023 date of the completion of the Works. Each report shall include: : (a) an executivesummary; ; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; ; (c) details of work subcontracted and the performance ofSub-contractors; ; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; ; (e) records of manpower and Contractor's equipment on theSite; ; (f) copies for that month of quality assurance documents, test results and certificates; ; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; ; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; ; (i) details of any unresolved disputes or claims, in relation to theProject; ; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; ; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; ; (l) details of various royalty payment and insurances required to be taken by the Contractor;and Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. . (n) details of defects by theAuthority; ; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; ; (p) any Material AdverseEffect; ; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; ; (r) declaration specifying compliance with all Manuals provided to the Contractor;and Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the Contract AgreementPage 73 of 251 Construction of Service Road and RCC Drain on both sides of NH 37A from Kaliabor –Tiniali- (Km 0.000) to Kolong Bridge (Km 0.600) in Nagaon district in the state of Assam under EPC Mode Nov 2023 date of the completion of the Works. Each report shall include: : (a) an executivesummary; ; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; ; (c) details of work subcontracted and the performance ofSub-contractors; ; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; ; (e) records of manpower and Contractor's equipment on theSite; ; (f) copies for that month of quality assurance documents, test results and certificates; ; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; ; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; ; (i) details of any unresolved disputes or claims, in relation to theProject; ; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; ; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; ; (l) details of various royalty payment and insurances required to be taken by the Contractor;and Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. . (n) details of defects by theAuthority; ; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; ; (p) any Material AdverseEffect; ; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; ; (r) declaration specifying compliance with all Manuals provided to the Contractor;and Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Construction Contract

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:: Contract AgreementPage 72 of 146 Widening/Improvement to 2-lane with earthen shoulder of Xxxxx Corner to Ukhrul section from existing km 34+650 to km 50+520 (Design Chainage km 30+970 to km 45+600) of NH-202 in the State of Manipur on EPC mode. (Package-3, Length-14.63 km) Jan 2024 (a) an executivesummary; ; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; ; (c) details of work subcontracted and the performance ofSub-contractors; ; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; ; (e) records of manpower and Contractor's equipment on theSite; ; (f) copies for that month of quality assurance documents, test results and certificates; ; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; ; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; ; (i) details of any unresolved disputes or claims, in relation to theProject; ; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; ; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; ; (l) details of various royalty payment and insurances required to be taken by the Contractor;and Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. . (n) details of defects by theAuthority; ; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; ; (p) any Material AdverseEffect; ; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; ; (r) declaration specifying compliance with all Manuals provided to the Contractor;and Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Contract Agreement

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:: Contract AgreementPage 72 of 146 “Construction of 2-lane Ukhrul bypass starting at km 537.850 of NH-202 & joining at km 8.840 of NH-102A (Ukhrul – Toloi – Tadubi Road) and continuing upto km 9.840 of NH- 102A (Package-1, Length-6.571 km) in the State of Manipur on EPC mode. (2nd Call)” Feb 2024 (a) an executivesummary; ; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; ; (c) details of work subcontracted and the performance ofSub-contractors; ; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; ; (e) records of manpower and Contractor's equipment on theSite; ; (f) copies for that month of quality assurance documents, test results and certificates; ; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; ; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; ; (i) details of any unresolved disputes or claims, in relation to theProject; ; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; ; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; ; (l) details of various royalty payment and insurances required to be taken by the Contractor;and Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. . (n) details of defects by theAuthority; ; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; ; (p) any Material AdverseEffect; ; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; ; (r) declaration specifying compliance with all Manuals provided to the Contractor;and Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Construction Contract

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:: Contract AgreementPage 72 of 146 “Construction of 2-lane Ukhrul bypass starting at km 537.850 of NH-202 & joining at km 8.840 of NH-102A (Ukhrul – Toloi – Tadubi Road) and continuing upto km 9.840 of NH- 102A (Package-1, Length-6.571 km) in the State of Manipur on EPC mode.” Dec 2023 (a) an executivesummary; ; (b) charts showing the status of Contractor's documents, construction and manufacturing and environmentalworks; ; (c) details of work subcontracted and the performance ofSub-contractors; ; (d) for the construction of each main part of the Works, the extent of progress (both quantity and percentage of the whole), the actual or expected dates of commencement, anticipated completion date of the activity, Contractor's inspections andtests; ; (e) records of manpower and Contractor's equipment on theSite; ; (f) copies for that month of quality assurance documents, test results and certificates; ; (g) safety statistics, accident data collection including details of any hazardous incidents and activities relating to environmental aspects and publicrelations; ; (h) comparisons of actual and planned progress, with details of any aspects which may jeopardise the completion in accordance with the Agreement, and the measures being (or to be) adopted to overcome suchaspects; ; (i) details of any unresolved disputes or claims, in relation to theProject; ; (j) details of any revision to the cash flow estimate, together with a copy of the revised cash flowestimate; ; (k) statusofvariousApplicablePermitsandcomplianceofconditionstherein; ; (l) details of various royalty payment and insurances required to be taken by the Contractor;and Contractor;and (m) such other reports as may be required by the Authority for enabling the AuthoritytocomplywithitsobligationsundertheotherProjectcontracts. . (n) details of defects by theAuthority; ; (o) change in emission of any sewage or effluent of any nature whatsoever, whether qualitatively orquantitatively; ; (p) any Material AdverseEffect; ; (q) declaration towards compliance with Applicable Laws including but not limited to environmental and labourlegislations; ; (r) declaration specifying compliance with all Manuals provided to the Contractor;and Contractor;and (s) any change in the flow of traffic in the existing ProjectHighway.

Appears in 1 contract

Samples: Construction Contract