Monthly Updates. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations. (See also Articles 2.1.2 and 2.1.5).
Appears in 78 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Monthly Updates. The Contractor Design-Builder must provide the Design Professional Program Manager and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations. (See also Articles 2.1.2 and 2.1.5).
Appears in 15 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Monthly Updates. The Contractor Design-Builder must provide the Design Professional Executive Administrator and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations. (See also Articles Sections 2.1.2 and 2.1.5).
Appears in 2 contracts
Samples: Design Build Contract, Construction Contract
Monthly Updates. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations. (See also Articles 2.1.2 and 2.1.5).
Appears in 1 contract