MTA Determination of an Excusable Delay Sample Clauses

MTA Determination of an Excusable Delay. The MTA shall review each received Extension Request and shall advise the SI of its decision on such Extension Request within a reasonable period, except that, where it is not reasonably practicable for the MTA to render such decision within a reasonable period, it shall advise the SI that it will require additional time and the approximate date upon which it expects to render a decision. If the MTA determines that an Excusable Delay has occurred, and that such Excusable Delay will extend the Substantial Completion Date or an Intermediate Milestone Date, then the MTA will extend the Substantial Completion Date (or applicable Intermediate Milestone Date), and the Engineer shall establish the scope and extent of the extension in light of the Excusable Delay's causes and effects, available mitigation, and other considerations determined by the Engineer (each, an "Excusable Delay Extension"). If applicable, the Engineer shall also issue a Change Order for Impact Costs pursuant to Section 5.16.4 (
AutoNDA by SimpleDocs

Related to MTA Determination of an Excusable Delay

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Penalty Determination H&SC section 39619.7 requires CARB to provide information on the basis for the penalties it seeks. This Agreement includes this information, which is also summarized here. The provision of law the penalty is being assessed under and why that provision is most appropriate for that violation. The penalty provision being applied in this case is H&SC section 42402 et seq. because IIT sold, supplied, offered for sale, consumer products for commerce in California in violation of the Consumer Products Regulations (17 CCR section 94507 et seq.). The penalty provisions of H&SC section 42402 et seq. apply to violations of the Consumer Products Regulations because the regulations were adopted under authority of H&SC section 41712, which is in Part 4 of Division 26. The manner in which the penalty amount was determined, including aggravating and mitigating factors and per unit or per vehicle basis for the penalty. H&SC section 42402 et seq. provides strict liability penalties of up to $10,000 per day for violations of the Consumer Product Regulations with each day being a separate violation. In cases like this, involving unintentional violations of the Consumer Products Regulations where the violator cooperates with the investigation, CARB has obtained penalties for selling uncertified charcoal lighter material in California. In this case, the total penalty is $7,500 for selling uncertified charcoal lighter material in California. The penalty in this case was reduced because this was a strict liability first-time violation and IIT made diligent efforts to cooperate with the investigation. To come into compliance, IIT no longer offers Safegel BBQ & Fireplace Lighting Gel Fire Starter for commerce in California. Final penalties were determined based on the unique circumstances of this matter, considered together with the need to remove any economic benefit from noncompliance, the goal of deterring future violations and obtaining swift compliance, the consideration of past penalties in similar negotiated cases, and the potential cost and risk associated with litigating these particular violations. The penalty reflects violations extending over a number of days resulting in quantifiable harm to the environment considered together with the complete circumstances of this case. Penalties in future cases might be smaller or larger on a per ton basis. The final penalty in this case was based in part on confidential financial information or confidential business information provided by IIT that is not retained by CARB in the ordinary course of business. The penalty in this case was also based on confidential settlement communications between CARB and IIT that CARB does not retain in the ordinary course of business. The penalty also reflects CARB’s assessment of the relative strength of its case against IIT, the desire to avoid the uncertainty, burden and expense of litigation, obtain swift compliance with the law and remove any unfair advantage that IIT may have secured from its actions. Is the penalty being assessed under a provision of law that prohibits the emission of pollution at a specified level, and, if so a quantification of excess emissions, if it is practicable to do so. The Consumer Product Regulations do not prohibit emissions above a specified level, but they do limit the concentration of VOCs in regulated products. In this case, a quantification of the excess emissions attributable to the violations was not practicable.

  • Salary Determination 12.5.1 A unit member shall receive a salary not less than the minimum salary nor more than the maximum salary (Articles 12.3 and 12.4) for the rank to which appointed, except as provided in Articles 4.15, 5.6, 10.6.1 or Article 10.6.1.1. The effective dates for salaries shall be the appropriate dates specified in Article 12.2.2.

  • Termination Due to Force Majeure Event If the period of Force Majeure continues or is in the reasonable judgment of the Parties likely to continue beyond a period of 120 (one hundred and twenty) Days, the Parties may mutually decide to terminate this Agreement or continue this Agreement on mutually agreed revised terms. If the Parties are unable to reach an agreement in this regard, the Affected Party shall after the expiry of the said period of 120 (one hundred and twenty ) Days be entitled to terminate the Agreement in which event, the provisions of Articles 16 and 17 shall, to the extent expressly made applicable, apply.

  • Termination due to Force Majeure 13.5.1 If the Force Majeure Event or its effects continue to be present beyond the period as specified in Article 4.5.3, either Party shall have the right to cause termination of the Agreement. In such an event, this Agreement shall terminate on the date of such Termination Notice.

  • Independence from Material Breach Determination Except as set forth in Section X.D.1.c, these provisions for payment of Stipulated Penalties shall not affect or otherwise set a standard for OIG’s decision that CHSI has materially breached this CIA, which decision shall be made at OIG’s discretion and shall be governed by the provisions in Section X.D, below.

  • Termination for Force Majeure In the event of a force majeure that lasts longer than thirty (30) days from the date that a Party claiming relief due to the force majeure event gives notice to the other Party, the Party not claiming relief under the force majeure event may terminate this Agreement upon written notice to the other Party. For the avoidance of doubt, the COVID-19 pandemic does not constitute a force majeure event.

  • Liability Calculation Method Per Claim Unless subject to a fixed dollar copayment, the calculation of Member liability on claims for Out-of-Area Covered Health Care Services processed through the BlueCard Program will be based on the lower of the provider’s billed charges or the negotiated price made available to Blue Shield by the Host Blue. Host Blues determine a negotiated price, which is reflected in the terms of each Host Blue’s health care provider contracts. The negotiated price made available to Blue Shield by the Host Blue may be represented by one of the following:

  • Termination Notice for Force Majeure Event If a Force Majeure Event subsists for a period of 180 (one hundred and eighty) days or more within a continuous period of 365 (three hundred and sixty five) days, either Party may in its discretion terminate this Agreement by issuing a Termination Notice to the other Party without being liable in any manner whatsoever, save as provided in this Article 34, and upon issue of such Termination Notice, this Agreement shall, notwithstanding anything to the contrary contained herein, stand terminated forthwith; provided that before issuing such Termination Notice, the Party intending to issue the Termination Notice shall inform the other Party of such intention and grant 15 (fifteen) days time to make a representation, and may after the expiry of such 15 (fifteen) days period, whether or not it is in receipt of such representation, in its sole discretion issue the Termination Notice.