NO DAMAGE FOR CONTRACTOR CAUSED DELAY Sample Clauses

NO DAMAGE FOR CONTRACTOR CAUSED DELAY. Notwithstanding anything to the contrary contained herein, Contractor shall not be entitled to any time extension or compensation, including, without limitation, extended field or home office overhead, field supervision, costs of capital, interest, escalation charges, acceleration costs or other impacts for any delays caused in whole or in part by Contractor's failure to perform its obligations under the Contract.
AutoNDA by SimpleDocs
NO DAMAGE FOR CONTRACTOR CAUSED DELAY. 15.11.1 Contractor shall not be entitled to any compensation, including but no limited to extended field or home office overhead, field supervision, costs of capital, interest, escalation charges, acceleration costs or other impacts for any delays caused in whole or in part by Contractor's failure to perform its obligations under this Contract, or during periods of delay concurrently caused by Contractor and either the County or others. Contractor may be compensated for delays caused directly and solely by the County except that Contractor shall not be entitled to damages for delay to the Work caused by the following reasons:
NO DAMAGE FOR CONTRACTOR CAUSED DELAY. Contractor shall not be entitled to additional compensation for extended field or home office overhead, field supervision, costs of capital, interest, escalation charges, acceleration costs, or other impacts for any delays to the extent such delays are caused by the failure of the Contractor or any subcontractor or other entity engaged in performance of the Work to perform the Work in accordance with the Contract Documents. Contractor may be eligible for additional compensation in excess of the Contract Price for delays caused by the Agency and/or its privities, as provided in subsection 7.4.

Related to NO DAMAGE FOR CONTRACTOR CAUSED DELAY

  • Liability for loss or damage Subject to the provisions of the Occupiers Liability Act 1957 and the Defective Premises Act 1972, we shall not in any circumstances incur any liability in respect of loss or damage to any person or property or otherwise, unless the loss or damage was caused by our negligence.

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Liability for Damage Each party shall be liable to the other for all damage to the property of the other negligently, recklessly or intentionally caused by that party (or their agents, employees or invitees), except to the extent the loss is insured and subrogation is waived under the owner's policy.

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following: