Notice by Contractor Required. The Contractor shall within five (5) calendar days of beginning of any such delay notify the Owner in writing of causes of delay with justification and supporting documentation. Claims relating to time extensions shall be made in accordance with applicable provisions of Article 7.
Appears in 4 contracts
Samples: Agreement Form, Agreement, Escrow Agreement