Common use of Notice of Impact Clause in Contracts

Notice of Impact. In addition to its obligations under Section 13.5.2.1, if Contractor claims there is a Force Majeure condition, Contractor shall (i) promptly notify Owner, in writing of the nature, cause and cost of such Force Majeure condition, (ii) state whether and to what extent the condition will delay the Guaranteed Mechanical Completion Date, the Delay Default Date, the Commercial Operation Date or Final Completion Date, (iii) state the date and time the Force Majeure condition commenced; and (iii) state whether Contractor recommends that Owner initiate a Change Order pursuant to Article 8.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

AutoNDA by SimpleDocs

Notice of Impact. In addition to its obligations under Section 13.5.2.1, if Contractor claims there is a Force Majeure condition, Contractor shall (i) promptly notify Owner, in writing of the nature, cause and cost of such Force Majeure condition, (ii) state whether and to what extent the condition will delay the Guaranteed Mechanical Completion Date, the Delay Default Date, the Commercial Operation Substantial Completion Date or Final Completion Date, (iii) state the date and time the Force Majeure condition commenced; and (iii) state whether Contractor recommends that Owner initiate a Change Order pursuant to Article 8.

Appears in 1 contract

Samples: Master Engineering, Procurement and Construction Agreement (SolarBank Corp)

AutoNDA by SimpleDocs

Notice of Impact. In addition to its obligations under Section 13.5.2.1, if Contractor claims there is a Force Majeure condition, Contractor shall (i) promptly notify Owner, in writing of the nature, cause and cost of such Force Majeure condition, (ii) state whether and to what extent the condition will delay the Guaranteed Mechanical Completion Date, the Delay Default Date, the Commercial Operation Date or Final Completion Date, (iii) state the date and time the Force Majeure condition commenced; and (iii) state whether Contractor recommends that Owner initiate a Change Order pursuant to Article 8.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (SolarBank Corp)