Common use of Obligation to Supply Reactive Power Clause in Contracts

Obligation to Supply Reactive Power. Project Developer agrees, as and when so directed by Transmission Provider or when so directed by the Transmission Owner acting on behalf or at the direction of Transmission Provider, to operate the Generating Facility to produce reactive power within the design limitations of the Generating Facility pursuant to voltage schedules, reactive power schedules or power factor schedules established by Transmission Provider or, as appropriate, the Transmission Owner. Transmission Provider shall maintain oversight over such schedules to ensure that all sources of reactive power in the PJM Region, as applicable, are treated in an equitable and not unduly discriminatory manner. Project Developer agrees that Transmission Provider and the Transmission Owner, acting on behalf or at the direction of Transmission Provider, may make changes to the schedules that they respectively establish as necessary to maintain the reliability of the Transmission System.

Appears in 12 contracts

Samples: Generation Interconnection Agreement, Generation Interconnection Agreement, Generation Interconnection Agreement

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.