Obligations of the Authority. 4.1.1 The Authority shall, at its own cost and expense, undertake, comply with and perform all its obligations set out in this Agreement or arising hereunder. 4.1.2 The Authority shall be responsible for the correctness of the Scope of the Project, Project Facilities, Specifications and Standards and the criteria for testing of the completed Works. 4.1.3 The Authority shall provide to the Contractor: (a) upon receiving the Performance Security under Clause 7.1.1, the Right of Way in accordance with the provisions of Clauses 8.2 and 8.3, within a period of 30 (thirty) days from the date of this Agreement, on no less than 90% (ninety per cent) of the total length of the Project Highway; (b) Deleted (c) Deleted. (Environmental clearances for the Project Highway are not required). 4.1.4 Delay in providing the Right of Way or approval of GAD by railway authorities, as the case may be, in accordance with the provisions of Clause
Appears in 4 contracts
Samples: Draft Contract Agreement for Construction, Draft Contract Agreement, Contract Agreement
Obligations of the Authority. 4.1.1 The Authority shall, at its own cost and expense, undertake, comply with and perform all its obligations set out in this Agreement or arising hereunder.
4.1.2 The Authority shall be responsible for the correctness of the Scope of the Project, Project Facilities, Specifications and Standards and the criteria for testing of the completed Works.
4.1.3 The Authority shall provide to the Contractor:
(a) upon receiving the Performance Security under Clause 7.1.1, the Right of Way in accordance with the provisions of Clauses 8.2 and 8.3, within 8.3,within a period of 30 15 (thirtyfifteen) days from the date of this Agreement, on no less than 90% (ninety per cent) of the total length of the Project Highway;
(b) Deleted.
(c) Deleted. (Environmental clearances for the Project Highway are not required).
4.1.4 Delay in providing the Right of Way or approval of GAD by railway authorities, as the case may be, in accordance with the provisions of Clause
Appears in 3 contracts
Samples: Epc Agreement, Epc Agreement, Epc Agreement
Obligations of the Authority. 4.1.1 The Authority shall, at its own cost and expense, undertake, comply with and perform all its obligations set out in this Agreement or arising hereunder.
4.1.2 The Authority shall be responsible for the correctness of the Scope of the Project, Project Facilities, Specifications and Standards and the criteria for testing of the completed Works.
4.1.3 The Authority shall provide to the Contractor:
(a) upon receiving the Performance Security under Clause 7.1.1, the Right of Way in accordance with the provisions of Clauses 8.2 and 8.3, within a period of 30 15 (thirtyfifteen) days from the date of this Agreement, on no less than 90% (ninety per cent) of the total length of the Project Highway;
(b) Deleted.
(c) Deleted. (Environmental clearances for the Project Highway are not required).
4.1.4 Delay in providing the Right of Way or approval of GAD by railway authorities, as the case may be, in accordance with the provisions of Clause
Appears in 2 contracts
Samples: Epc Agreement, Epc Agreement
Obligations of the Authority. 4.1.1 The Authority shall, at its own cost and expense, undertake, comply with and perform all its obligations set out in this Agreement or arising hereunder.
4.1.2 The Authority shall be responsible for the correctness of the Scope of the Project, Project Facilities, Specifications and Standards and the criteria for testing of the completed Works.
4.1.3 The Authority shall provide to the Contractor:
(a) upon receiving the Performance Security under Clause 7.1.1, the Right of Way in accordance with the provisions of Clauses 8.2 and 8.3, within a period of 30 (thirty) days from the date of this Agreement, on no less than 90% (ninety per cent) of the total length of the Project Highway;
(b) Deleted
(c) Deleted. (Environmental clearances for the Project Highway are not required).
4.1.4 Delay in providing the Right of Way or approval of GAD by railway authorities, as the case may be, in accordance with the provisions of Clause
Appears in 1 contract
Samples: Engineering, Procurement & Construction (Epc) Agreement
Obligations of the Authority. 4.1.1 The Authority shall, at its own cost and expense, undertake, comply with and perform all its obligations set out in this Agreement or arising hereunder.
4.1.2 The Authority shall be responsible for the correctness of the Scope of the Project, Project Facilities, Specifications and Standards and the criteria for testing of the completed Works.
4.1.3 The Authority shall provide to the Contractor:
(a) upon receiving the Performance Security under Clause 7.1.1, the Right of Way in accordance with the provisions of Clauses 8.2 and 8.3, within a period of 30 (thirty) days from the date of this Agreement, on no less than 90% (ninety per cent) of the total length of the Project Highway;
(b) Deleted
(c) Deleted. (Environmental clearances for the Project Highway are not required).
4.1.4 Delay in providing the Right of Way or approval of GAD by railway authorities, as the case may be, in accordance with the provisions of Clause 4.1.3 shall entitle the Contractor to Damages in a sum calculated in accordance with the provisions of Clause
Appears in 1 contract
Samples: Draft Contract Agreement (Dca)
Obligations of the Authority. 4.1.1 The Authority shall, at its own cost and expense, undertake, comply with and perform all its obligations set out in this Agreement or arising hereunder.
4.1.2 The Authority shall be responsible for the correctness of the Scope of the Project, Project Facilities, Specifications and Standards and the criteria for testing of the completed Works.
4.1.3 The Authority shall provide to the Contractor:
(a) upon receiving the Performance Security under Clause 7.1.1, the Right of Way in accordance with the provisions of Clauses 8.2 and 8.3, within a period of 30 (thirty) days from the date of this Agreement, on no less than 90% (ninety per cent) of the total length of the Project Highway;
(b) Deleted
(c) Deleted. (Environmental clearances for the Project Highway are not required).
4.1.4 Delay in providing the Right of Way or approval of GAD by railway authorities, as the case may be, in accordance with the provisions of Clause 4.1.3 shall entitle the Contractor to Damages in a sum calculated in accordance with the provisions of Clause 8.3 of this Agreement and Time Extension in accordance with the provisions of Clause
Appears in 1 contract
Samples: Draft Contract Agreement