OWNER-FURNISHED ITEMS; CONSTRUCTION OR INSTALLATION PROCEDURES. 3.9.1 The Construction Manager accepts assignment of, and liability for, all purchase orders and other agreements for procurement of materials and equipment that are identified as part of the Contract Documents and have been provided to it prior to or during the execution of the Contract. The Construction Manager shall be responsible for such Owner-furnished items, if any, as if the Construction Manager were the original purchaser. If feasible, the Construction Manager shall promptly inspect all Owner-furnished items and report to the Owner any deficiencies or defects. Failure to so report shall constitute an acknowledgment that such items are fit and suitable for inclusion in the Work. All warranty and Correction of the Work obligations under the Contract Documents shall also apply to any Owner-furnished items, unless the Contract Documents specifically provide otherwise. 3.9.2 The Construction Manager shall review any specified construction or installation procedure (including those recommended by any product manufacturer). The Construction Manager shall advise the Owner: procedure. (a) if the specified procedure deviates from acceptable construction practice; (b) if following the procedure will affect any warranties; or (c) of any objections which the Construction Manager may have to the
Appears in 4 contracts
Samples: Professional Services, Professional Services Agreement, Professional Services
OWNER-FURNISHED ITEMS; CONSTRUCTION OR INSTALLATION PROCEDURES. 3.9.1 The Construction Manager accepts assignment of, and liability for, all purchase orders and other agreements for procurement of materials and equipment that are identified as part of the Contract Documents and have been provided to it prior to or during the execution of the Contract. The Construction Manager shall be responsible for such Owner-furnished items, if any, as if the Construction Manager were the original purchaser. If feasible, the Construction Manager shall promptly inspect all Owner-furnished items and report to the Owner any deficiencies or defects. Failure to so report shall constitute an acknowledgment that such items are fit and suitable for inclusion in the Work. All warranty and Correction of the Work obligations under the Contract Documents shall also apply to any Owner-furnished items, unless the Contract Documents specifically provide otherwise.
3.9.2 The Construction Manager shall review any specified construction or installation procedure (including those recommended by any product manufacturer). The Construction Manager shall advise the Owner: procedure.:
(a) if the specified procedure deviates from acceptable construction practice;
(b) if following the procedure will affect any warranties; or
(c) of any objections which the Construction Manager may have to thethe procedure.
Appears in 1 contract
Samples: Professional Services Agreement
OWNER-FURNISHED ITEMS; CONSTRUCTION OR INSTALLATION PROCEDURES. 3.9.1 The Construction Manager accepts assignment of, and liability for, all purchase orders and other agreements for procurement of materials and equipment that are identified as part of the Contract Documents and have been provided to it prior to or during the execution of the Contract. The Construction Manager shall shallwill be responsible for such Owner-furnished items, if any, as if the Construction Manager were the original purchaser. If feasible, the Construction Manager shall shallwill promptly inspect all Owner-Owner- furnished items and report to the Owner any deficiencies or defects. Failure to so report shall shallwill constitute an acknowledgment that such items are fit and suitable for inclusion in the Work. All warranty and Correction of the Work obligations under the Contract Documents shall shallwill also apply to any Owner-Owner- furnished items, unless the Contract Documents specifically provide otherwise.
3.9.2 The Construction Manager shall shallwill review any specified construction or installation procedure (including those recommended by any product manufacturer). The Construction Manager shall shallwill advise the Owner: procedure.:
(a) if the specified procedure deviates from acceptable construction practice;
(b) if following the procedure will affect any warranties; or
(c) of any objections which the Construction Manager may have to thethe procedure.
Appears in 1 contract
Samples: Construction Management Agreement