Common use of Partial Occupancy and Use Clause in Contracts

Partial Occupancy and Use. Prior to Contractor’s achieving Substantial Completion, Owner may occupy or use all or any portion of the Work then capable of functioning safely, provided that such occupancy or use is authorized by the Governmental Instrumentality and Owner’s insurance company or companies providing property insurance and builder’s risk coverage have consented to such partial occupancy or use. Contractor shall assist Owner and take reasonable steps in obtaining consent of the insurance company or companies and applicable Government Instrumentalities. Immediately prior to such partial occupancy or use, Owner and Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work and all personnel and environmental safety aspects of the Work. Such occupancy or use shall not in any way release Contractor or any surety of Contractor from any obligations or liabilities pursuant to this Agreement, including the obligation to engineer, procure and construct the Facility in accordance with all requirements of this Agreement; provided, however, Contractor shall be entitled to a Change Order for an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, and adjustment to the Contract Price, to the extent Owner’s partial occupancy or use of the Facility delays the prosecution or completion of the Work, or increases Contractor’s cost of performing the Work, and Contractor satisfies the requirements for such time extension and Contract Price adjustment pursuant to Section 6.8. Such occupancy or use shall not be deemed to be an acceptance by Owner of such portion of the Facility.

Appears in 2 contracts

Samples: Lump Sum Turnkey Agreement (Mirant Corp), Lump Sum Turnkey Agreement (Mirant Corp)

AutoNDA by SimpleDocs

Partial Occupancy and Use. Prior to Contractor’s Contractor achieving Substantial CompletionCompletion of a Train, Owner may may, upon giving written notice to Contractor, occupy or and use all or any portion of the buildings (excluding warehouses) identified in Attachment A for such Train (and with the Parties’ mutual agreement, any other portion of the Work related to such Train) then capable of functioning safely, provided that such occupancy or use is authorized by the Governmental Instrumentality (to the extent such authorization is necessary) and Owner’s insurance company or companies providing property insurance and builder’s risk coverage have consented to such partial occupancy or use (to the extent such consent is necessary) and Owner shall insure that portion of such buildings it takes occupancy and use upon taking such occupancy and use. Contractor shall assist Owner and take reasonable steps in obtaining consent of the insurance company or companies and applicable Government Governmental Instrumentalities. Immediately prior to such partial occupancy or use, Owner and Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work and all personnel and environmental safety aspects of the WorkWork and Owner shall insure such building(s) immediately upon taking over such building(s). Such occupancy or use shall not in any way release Contractor or any surety of Contractor from any obligations or liabilities pursuant to this Agreement, including the obligation to engineer, procure and construct a fully operational natural gas liquefaction facility and export terminal within the Facility required times set forth in the Key Dates and otherwise in accordance with all requirements of this Agreement; provided, however, Contractor nor shall be entitled to a Change Order for an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, and adjustment to the Contract Price, to the extent Owner’s partial such occupancy or use of the Facility delays the prosecution or completion of the Work, or increases Contractor’s cost of performing the Work, and Contractor satisfies the requirements for such time extension and Contract Price adjustment pursuant to Section 6.8. Such occupancy or use shall not be deemed to be an acceptance by Owner of such portion of the FacilityWork. For any portion of the Work that Owner occupies and uses pursuant to this Section 11.8, the Defect Correction Period for that portion of the Work shall commence upon Owner’s occupancy and use of such portion of the Work and the risk of loss for such portion of the Work shall transfer to Owner, notwithstanding Section 8.2; provided that, the risk of loss shall not transfer, and the Defect Correction Period shall not commence, for any Equipment housed but not operating within such portion of the Work (other than HVAC and lighting).

Appears in 1 contract

Samples: Fixed Price Turnkey Agreement (NextDecade Corp.)

Partial Occupancy and Use. Prior to Contractor’s Contractor achieving Substantial Completion, Owner may may, upon giving written notice to Contractor, occupy or and use all or any portion of the buildings (excluding warehouses) identified in Attachment A for Train 4 (and with the Parties’ mutual agreement, any other portion of the Work related to Train 4) then capable of functioning safely, provided that such occupancy or use is authorized by the Governmental Instrumentality (to the extent such authorization is necessary) and Owner’s insurance company or companies providing property insurance and builder’s risk coverage have consented to such partial occupancy or use (to the extent such consent is necessary) and Owner shall insure that portion of such buildings it takes occupancy and use upon taking such occupancy and use. Contractor shall assist Owner and take reasonable steps in obtaining consent of the insurance company or companies and applicable Government Governmental Instrumentalities. Immediately prior to such partial occupancy or use, Owner and Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work and all personnel and environmental safety aspects of the WorkWork and Owner shall insure such building(s) immediately upon taking over such building(s). Such occupancy or use shall not in any way release Contractor or any surety of Contractor from any obligations or liabilities pursuant to this Agreement, including the obligation to engineer, procure and construct a fully operational natural gas liquefaction facility and export terminal within the Facility required times set forth in the Key Dates and otherwise in accordance with all requirements of this Agreement; provided, however, Contractor nor shall be entitled to a Change Order for an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, and adjustment to the Contract Price, to the extent Owner’s partial such occupancy or use of the Facility delays the prosecution or completion of the Work, or increases Contractor’s cost of performing the Work, and Contractor satisfies the requirements for such time extension and Contract Price adjustment pursuant to Section 6.8. Such occupancy or use shall not be deemed to be an acceptance by Owner of such portion of the FacilityWork. For any portion of the Work that Owner occupies and uses pursuant to this Section 11.8, the Defect Correction Period for that portion of the Work shall commence upon Owner’s occupancy and use of such portion of the Work and the risk of loss for such portion of the Work shall transfer to Owner, notwithstanding Section 8.2; provided that, the risk of loss shall not transfer, and the Defect Correction Period shall not commence, for any Equipment housed but not operating within such portion of the Work (other than HVAC and lighting).

Appears in 1 contract

Samples: Fixed Price Turnkey Agreement (NextDecade Corp.)

Partial Occupancy and Use. Prior to Contractor’s Contractor achieving Substantial Completion, Owner may occupy or use all or any portion of the Work then capable of functioning safely, provided that such occupancy or use is authorized by the applicable Governmental Instrumentality and Owner’s insurance company or companies providing property insurance and builder’s risk coverage have consented to such partial occupancy or use. Contractor shall assist Owner and take reasonable steps in obtaining consent of the insurance company or companies and applicable Government Instrumentalities. Immediately prior to such partial occupancy or use, Owner and Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work and all personnel and environmental safety aspects of the Work. Such occupancy or use shall not in any way release Contractor or any surety of Contractor from any obligations or liabilities pursuant to this Agreement, including the obligation to engineer, procure and construct a fully operational Project within the Facility required times set forth in the Milestone Dates and otherwise in accordance with all requirements of this Agreement; provided, however, Contractor nor shall be entitled to a Change Order for an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, and adjustment to the Contract Price, to the extent Owner’s partial such occupancy or use of the Facility delays the prosecution or completion of the Work, or increases Contractor’s cost of performing the Work, and Contractor satisfies the requirements for such time extension and Contract Price adjustment pursuant to Section 6.8. Such occupancy or use shall not be deemed to be an acceptance by Owner of such portion of the FacilityWork. However, to the extent such occupancy or use causes delays to the Work of the Contractor, Contractor shall be entitled to an extension of time and an increase in the Contract Price due to such delay to the extent permitted in Section 6.8. Without limitation of the foregoing, but subject to Contractor’s right to seek an extension of time as described in this Section 12.7, Contractor shall be liable for any and all Delay Liquidated Damages for failing to achieve Substantial Completion as set forth in this Agreement, regardless of whether Owner is using or occupying a portion of the Work.

Appears in 1 contract

Samples: Turnkey Agreement (Global Clean Energy Holdings, Inc.)

Partial Occupancy and Use. Prior to Contractor’s Contractor achieving Substantial CompletionCompletion of any Train, Owner may may, upon giving written notice to Contractor, occupy or use all or any portion of the Work any usable building or road then capable of functioning safely, provided that such occupancy or use is authorized by the Governmental Instrumentality (to the extent such authorization is necessary) and Owner’s insurance company or companies providing property insurance and builder’s risk coverage have consented to such partial occupancy or useuse (to the extent such consent is necessary). Contractor shall assist Owner and take reasonable steps in obtaining consent of the insurance company or companies and applicable Government Governmental Instrumentalities. Immediately prior to such partial occupancy or use, Owner and Contractor shall jointly inspect the area that portion of any usable building or road to be occupied or portion of the Work to be used in order to determine and record the condition of the Work such portion of such usable building or road and all personnel and environmental safety aspects relating thereto. Upon such occupancy by Owner, Contractor shall connect all necessary utilities, security, and telephones, and provide furnishings (as applicable) as further specified in Attachment A and Owner shall insure such portion of the usable building immediately upon taking over such building and Owner’s use or occupancy shall not interfere with or disrupt Contractor’s completion of the Work. Such occupancy or use shall not in any way release Contractor or any surety of Contractor from any obligations or liabilities pursuant to this Agreement, including the obligation to engineer, procure and construct a fully operational natural gas liquefaction facility within the Facility required times set forth in the Guaranteed Dates and otherwise in accordance with all requirements of this Agreement; provided, however, Contractor nor shall be entitled to a Change Order for an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, and adjustment to the Contract Price, to the extent Owner’s partial such occupancy or use of the Facility delays the prosecution or completion of the Work, or increases Contractor’s cost of performing the Work, and Contractor satisfies the requirements for such time extension and Contract Price adjustment pursuant to Section 6.8. Such occupancy or use shall not be deemed to be an acceptance by Owner of such portion of the FacilityWork provided however, if Owner’s use or occupancy under this Section 11.7 adversely affects Contractor’s or its Subcontractors’ or Sub-subcontractors’ cost or time for performance of the Work in accordance with the requirements of this Agreement, then Contractor shall be entitled to a Change Order pursuant to Section 6.2A.5 and Section 6.8. For any portion of the Work that Owner occupies and uses pursuant to this Section 11.7, the Defect Correction Period for that portion of the Work shall commence upon Owner’s occupancy and use of such portion of the Work and the risk of loss for such portion of the Work shall transfer to Owner, notwithstanding Section 8.2.

Appears in 1 contract

Samples: Fixed Price Separated Turnkey Agreement (Cheniere Energy, Inc.)

AutoNDA by SimpleDocs

Partial Occupancy and Use. Prior to Contractor’s Contractor achieving Substantial Completion, Owner may occupy or use all or any portion of the Work then capable of functioning safely, provided that such occupancy or use is authorized by the applicable Governmental Instrumentality and Owner’s insurance company or companies providing property insurance and builder’s risk coverage have consented to such partial occupancy or use. Contractor shall assist Owner and take reasonable steps in obtaining consent of the insurance company or companies and applicable Government Instrumentalities. Immediately prior to such partial occupancy or use, Owner and Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work and all personnel and environmental safety aspects of the Work. Such occupancy or use shall not in any way release Contractor or any surety of Contractor from any obligations or liabilities pursuant to this Agreement, including the obligation to engineer, procure and construct a fully operational Project within the Facility required times set forth in the Milestone Dates and otherwise in accordance with all requirements of this Agreement; provided, however, Contractor nor shall be entitled to a Change Order for an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, and adjustment to the Contract Price, to the extent Owner’s partial such occupancy or use of the Facility delays the prosecution or completion of the Work, or increases Contractor’s cost of performing the Work, and Contractor satisfies the requirements for such time extension and Contract Price adjustment pursuant to Section 6.8. Such occupancy or use shall not be deemed to be an acceptance by Owner of such portion of the FacilityWork. However, to the extent such occupancy or use causes delays to the Work of the Contractor, Contractor shall be entitled to an extension of time and an increase in the Compensation due to such delay to the extent permitted in Section 6.8. Without limitation of the foregoing, but subject to Contractor’s right to seek an extension of time as described in this Section 12.7, Contractor shall be liable for any and all Delay Liquidated Damages for failing to achieve Substantial Completion as set forth in this Agreement, regardless of whether Owner is using or occupying a portion of the Work.

Appears in 1 contract

Samples: Turnkey Agreement (Global Clean Energy Holdings, Inc.)

Partial Occupancy and Use. Prior to Contractor’s Contractor achieving Substantial Completion, Owner may may, upon giving written notice to Contractor, occupy or and use all or any portion of the buildings (excluding warehouses) identified in Attachment A for Train 3 (and with the Parties’ mutual agreement, any other portion of the Work related to such Train) then capable of functioning safely, provided that such occupancy or use is authorized by the Governmental Instrumentality (to the extent such authorization is necessary) and Owner’s insurance company or companies providing property insurance and builder’s risk coverage have consented to such partial occupancy or use (to the extent such consent is necessary) and Owner shall insure that portion of such buildings it takes occupancy and use upon taking such occupancy and use. Contractor shall assist Owner and take reasonable steps in obtaining consent of the insurance company or companies and applicable Government Governmental Instrumentalities. Immediately prior to such partial occupancy or use, Owner and Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work and all personnel and environmental safety aspects of the WorkWork and Owner shall insure such building(s) immediately upon taking over such building(s). Such occupancy or use shall not in any way release Contractor or any surety of Contractor from any obligations or liabilities pursuant to this Agreement, including the obligation to engineer, procure and construct a fully operational natural gas liquefaction facility and export terminal within the Facility required times set forth in the Key Dates and otherwise in accordance with all requirements of this Agreement; provided, however, Contractor nor shall be entitled to a Change Order for an extension to the Key Milestone Schedule, Guaranteed Substantial Completion Date and Required Final Completion Date, and adjustment to the Contract Price, to the extent Owner’s partial such occupancy or use of the Facility delays the prosecution or completion of the Work, or increases Contractor’s cost of performing the Work, and Contractor satisfies the requirements for such time extension and Contract Price adjustment pursuant to Section 6.8. Such occupancy or use shall not be deemed to be an acceptance by Owner of such portion of the FacilityWork. For any portion of the Work that Owner occupies and uses pursuant to this Section 11.8, the Defect Correction Period for that portion of the Work shall commence upon Owner’s occupancy and use of such portion of the Work and the risk of loss for such portion of the Work shall transfer to Owner, notwithstanding Section 8.2; provided that, the risk of loss shall not transfer, and the Defect Correction Period shall not commence, for any Equipment housed but not operating within such portion of the Work (other than HVAC and lighting).

Appears in 1 contract

Samples: Fixed Price Turnkey Agreement (NextDecade Corp.)

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!