PAYMENTS FOR EXTRA WORK. Written notice of claims for payments for extra work shall be given by the contractor within ten days after receipt of instructions from the owner as approved by the Engineer to proceed with the extra work and also before any work is commenced, except in emergency endangering the life or property. No claim shall be made valid unless so made. In all cases, the contractor's itemized estimate sheets showing all labor and material shall be submitted to the Engineer. The owner's order for extra work shall specify any extension of the contract time and one of the following methods of payments: a) Unit prices or combinations of unit prices which formed the basis of the original contract. b) A lump sum based on the contractor's estimate, accepted by the owner, and approved by the Engineer. c) Forced account as described in Section 2.6.19.