Penalty for Failure to Provide Requested Records. The Contractor shall provide all records and retrievals when requested. If such records are not received within fourteen (14) calendar days, the Authority may assess Liquidated Damages in the amount of One Hundred Dollars ($100) per day from the Contractor’s own funds for each item requested but not provided.
Appears in 2 contracts
Samples: www.mwaa.com, www.metwashairports.com
Penalty for Failure to Provide Requested Records. The As required by Section 6.04(a), the Contractor shall provide all records and retrievals when requestedupon seven (7) days advance notice. If such records are not received within fourteen (14) calendar days, the Authority may assess Liquidated Damages in the amount of One Hundred Dollars ($100) per day from the Contractor’s own funds for each item requested but not provided.
Appears in 2 contracts
Samples: Concession Management Contract, Concession Management Contract