PERFORMANCE AND SUPERINTENDENCE OF WORK BY PRIVATE ENTITY. a. The Private Entity shall be responsible for providing all the services called for by this Agreement. b. The Private Entity must give personal superintendence to the Work either in person or by having a xxxxxxx or superintendent on the Prime Construction Contractor’s or Private Entity’s payroll, approved by the Owner’s Representative, with authority to act on behalf of the Private Entity, on the site at all times Work is in progress. 1. A minimum of one such superintendent must be provided on site to be responsible for coordinating, directing, inspecting, and expediting the Work of the Prime Construction Contractor and its subcontractors. 2. It is contemplated that all Work will be performed during normal working hours, between the hours of 7:00 a.m. until 5:00 p.m., Monday through Friday, local time, unless otherwise specified in this Agreement. Work performed by the Private Entity at its own volition outside such normal working hours shall be at no additional expense to the Owner. The Private Entity’s material and equipment deliveries must not interfere with the arrival or departure of Owner employees, staff and visitors to existing facilities. c. The Private Entity must refer requests received from occupants of buildings included in the immediate Work area to change the hours of Work, including anticipated cost and schedule impact, to the Owner’s Representative for resolution. d. The Private Entity shall submit a daily construction report by close of business of the following working day on a form provided by or approved by the Owner’s Representative or other form customarily used in the industry. The report shall indicate the number of people by trade or craft, and the type and location of Work. The report shall include subcontractors, safety and quality violations observed, corrective measures taken to correct the violations, and other information requested by the Owner’s Representative. The Owner’s Representative may modify the requirements of this report as the Project progresses.
Appears in 2 contracts
Samples: Design and Construction Agreement, Comprehensive Agreement
PERFORMANCE AND SUPERINTENDENCE OF WORK BY PRIVATE ENTITY. a. The Private Entity shall be responsible for providing all the services called for by this Agreement.
b. The Private Entity must give personal superintendence to the Work either in person or by having a xxxxxxx or superintendent on the Prime Construction Contractor’s or Private Entity’s payroll, approved by the Owner’s Representative, with authority to act on behalf of the Private Entity, on the site at all times Work is in progress.
1. A minimum of one such superintendent must be provided on site to be responsible for coordinating, directing, inspecting, and expediting the Work of the Prime Construction Contractor and its subcontractors.
2. It is contemplated that all Work will be performed during normal working hours, between the hours of 7:00 a.m. until 5:00 p.m., Monday through Friday, local time, unless otherwise specified in this Agreement. Work performed by the Private Entity at its own volition outside such normal working hours shall be at no additional expense to the Owner. The Private Entity’s material and equipment deliveries must not interfere with the arrival or departure of Owner employees, staff and visitors to existing facilities.
c. The Private Entity must refer requests received from occupants of buildings included in the immediate Work area to change the hours of Work, including anticipated cost and schedule impact, to the Owner’s Representative Owner for resolution.
d. The Private Entity shall submit a daily construction report by close of business of the following working day on a form provided by or approved by the Owner’s Representative Owner or other form customarily used in the industry. The report shall indicate the number of people by trade or craft, and the type and location of Work. The report shall include subcontractors, safety and quality violations observed, corrective measures taken to correct the violations, and other information requested by the Owner’s Representative. The Owner’s Representative Owner may modify the requirements of this report as the Project progresses.
Appears in 1 contract
Samples: Comprehensive Agreement
PERFORMANCE AND SUPERINTENDENCE OF WORK BY PRIVATE ENTITY. a. The Private Entity shall be responsible for providing all the services Services called for by this Agreement. In addition, the Private Entity or its Contractor shall perform on the site, with its own organization, work equivalent to at least 10% percent of the total amount of Work to be performed under this Agreement. The percentage of Work required to be performed by the Private Entity or its Contractor may be reduced with written approval of the Owner’s Representative.
b. The Private Entity must give personal superintendence to the Work either in person or by having a xxxxxxx or superintendent on the Prime Construction Contractor’s or Private Entity’s payroll, approved by the Owner’s Representative, with authority to act on behalf of the Private Entity, on the site at all times Work is in progress.
1. A minimum of one such superintendent must be provided on site to be responsible for coordinating, directing, inspecting, and expediting the Work of the Prime Construction Contractor and its subcontractors.
2. It is contemplated that all Work will be performed during normal working hours, between the hours of 7:00 a.m. until 5:00 7:00 p.m., Monday through Friday, local time, unless otherwise specified in this AgreementAgreement or unless otherwise prohibited by the local jurisdiction. Work performed by the Private Entity at its own volition outside such normal working hours shall be at no additional expense to the Owner. The Private Entity’s material and equipment deliveries must not interfere with the arrival or departure of Owner employees, staff and visitors to existing facilities.
c. The Private Entity must refer requests received from occupants of buildings included in the immediate Work area to change the hours of Work, including anticipated cost and schedule impact, to the Owner’s Representative for resolution.
d. The Private Entity shall submit a daily construction report by close of business of the following working day on a form provided by or approved by the Owner’s Representative or other form customarily used in the industry. The report shall indicate the number of people by trade or craft, and the type and location of Work. The report shall include subcontractors, safety and quality violations observed, corrective measures taken to correct the violations, and other information requested by the Owner’s Representative. The Owner’s Representative may modify the requirements of this report as the Project progresses.
Appears in 1 contract
Samples: Comprehensive Agreement