Common use of Performance Suspension Clause in Contracts

Performance Suspension. 16.1 The Principal, by means of the Works Manager, shall be entitled to suspend the Contract, either totally or partially, at any time whatsoever and on more than one occasion, by providing the Contractor with written communication of the suspension sent by registered mail with return receipt. Said suspension cannot, in any case, exceed, as a whole, the overall duration of 45 (forty-five) calendar days. 16.2 The Contractor shall be entitled to receive a refund for the costs and expenses sustained due to suspension, which shall be provisionally defined (in order to permit continuation of the Works) by the Works Manager, except for the Parties being entitled to object the Works Manager’s decision pursuant to Article 24. The Parties shall undertake, in any case, to provisionally apply the Works Manager’s decision. 16.3 In the case of suspension arising pursuant to this Article, the Parties have accepted that the Project Implementation Schedule may be amended in agreement between the Parties. This extension must be at least equal to the period of suspension.

Appears in 4 contracts

Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)

AutoNDA by SimpleDocs

Performance Suspension. 16.1 The Principal, by means of the Works Manager, shall be entitled to suspend the Contract, either totally or partially, at any time whatsoever and on more than one occasion, by providing the Contractor with written communication of the suspension sent by registered mail with return receipt. Said suspension cannot, in any case, exceed, as a whole, the overall duration of 45 (forty-five) calendar days. 16.2 The Contractor shall be entitled to receive a refund for the costs and expenses sustained due to suspension, which shall be provisionally defined (in order to permit allow continuation of the Works) by the Works Manager, except for the Parties being entitled to object the Works Manager’s decision pursuant to Article 24. The Parties shall undertake, in any case, to provisionally apply the Works Manager’s decision. 16.3 In the case of suspension arising pursuant to this Article, the Parties have accepted that the Project Implementation Schedule may be amended in agreement between the Parties. This extension must be at least equal to the period of suspension.

Appears in 1 contract

Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)

AutoNDA by SimpleDocs