Periodic Review. After approval of the GMP Change Order, the Program Manager and the Design Builder shall review each proposed transfer to and from the Design Contingency on a weekly basis. The Owner shall have absolute control over transfers to and from the Design Contingency as well as the release of the contingency.
Appears in 14 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Periodic Review. After approval of the GMP Change Order, the Program Manager Executive Administrator and the Design Design-Builder shall review each proposed transfer to and from the Design Contingency on a weekly basis. The Owner shall have absolute control over transfers to and from the Design Contingency as well as the release of the contingency.
Appears in 2 contracts
Samples: Design Build Contract, Construction Contract