Permitted Change Orders. 9.5.1 Provided that Contractor has notified Owner as required and has used all reasonable efforts to avoid and mitigate any potential delays to the Project Schedule or increased Direct Costs resulting from such events, Contractor will, to the extent described in Sections 9.5.2 and 9.5.3, be entitled to receive Change Orders as and for the events described in this Section 9.5.1.
Appears in 3 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Permitted Change Orders. 9.5.1 Provided that Contractor has notified Owner as required and has used all reasonable efforts to avoid and mitigate any potential delays to the Project Schedule or increased Direct Costs resulting from such events, Contractor will, to the extent described in Sections 9.5.2 and 9.5.3, be entitled to receive Change Orders as and for the events described in this Section 9.5.19.5.
Appears in 2 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Permitted Change Orders. β
9.5.1 Provided that Contractor has notified Owner as required and has used all reasonable efforts to avoid and mitigate any potential delays to the Project Schedule or increased Direct Costs resulting from such events, Contractor will, to the extent described in Sections 9.5.2 and 9.5.3, be entitled to receive Change Orders as and for the events described in this Section 9.5.1.
Appears in 1 contract
Samples: Engineering, Procurement and Construction Agreement