Change Order Due to Change of Law Sample Clauses

Change Order Due to Change of Law. Subject to Section 9.5.1, if and to the extent that a Change of Law occurs that (a) directly delays Contractor in its ability to achieve any Key Milestone, then Owner will, via Change Order, extend the Project Schedule as described in Section 9.5.2, and/or (b) directly increases Contractor’s Direct Costs of performing the Work by more than $[ ], then Owner will, via Change Order, increase the Contract Price as described in Section 9.5.3. Change Order(s) issued under this Section 9.5.1(f) shall be Contractor’s sole and exclusive remedy and compensation for any additional costs and/or delays resulting from any Change of Law, and Contractor will not be entitled to any additional payment, damages or other compensation in connection therewith.
AutoNDA by SimpleDocs
Change Order Due to Change of Law. Subject to Section 9.5.1, if and to the extent that a Change of Law occurs that (a) directly delays Contractor in its ability to achieve any Key Milestone, then Owner will, via Change Order, extend the Project Schedule as described in Section 9.5.2, and/or (b) directly increases Contractor’s Direct Costs of performing the Work by more than $[____], then Owner will, via Change Order, increase the Contract Price as described in Section 9.5.3. Change Order(s) issued under this Section 9.5.1(f) shall be Contractor’s sole and exclusive remedy and compensation for any additional costs and/or delays resulting from any Change of Law, and Contractor will not be entitled to any additional payment, damages or other compensation in connection therewith. Changes Involving Schedule Extensions. To the extent that Contractor demonstrates that an event for which it is entitled to a Change as described in Section 9.5.1 is the sole cause of critical path delay to Contractor’s ability to perform the Work despite Contractor’s use of commercially reasonable efforts to mitigate and avoid any such delay, Owner shall issue a Change Order to extend the dates in the Project Schedule as necessary to accommodate such delay. Contractor’s demonstration of the impact on the critical path of the Work must be made on a basis that analyzes the actual impacts of the given event on the then-current schedule for completion of the Work. In no event will Contractor be entitled to an extension of time under this Section 9.5.2 to the extent that the performance of the Work for which the extension is sought would have been suspended, delayed or interrupted by the concurrent fault, actions or omissions of Contractor.

Related to Change Order Due to Change of Law

  • Termination for Changes in Budget or Law The JBE’s payment obligations under this Agreement are subject to annual appropriation and the availability of funds. Expected or actual funding may be withdrawn, reduced, or limited prior to the expiration or other termination of this Agreement. Funding beyond the current appropriation year is conditioned upon appropriation of sufficient funds to support the activities described in this Agreement. The JBE may terminate this Agreement or limit Contractor’s Services (and reduce proportionately Contractor’s fees) upon Notice to Contractor without prejudice to any right or remedy of the JBE if: (i) expected or actual funding to compensate Contractor is withdrawn, reduced or limited; or (ii) the JBE determines that Contractor’s performance under this Agreement has become infeasible due to changes in applicable laws.

  • TERMINATION DUE TO CHANGE IN FUNDING ‌ 35 In the event funding from HCA, MCO, State, Federal, or other sources is withdrawn, reduced, or limited 36 in any way after the effective date of this Contract and prior to its normal completion, either party may 37 terminate this Contract subject to re-negotiations.

  • Change of Schedule (a) (applicable to full-time employees only) Where an employee's schedule is changed by the Hospital with less than twenty-four (24) hours notice, she shall receive time and one-half (1½) of her regular straight time hourly rate for all hours worked on her next shift.

  • Contract Renegotiation, Suspension, or Termination Due to Change in Funding If the funds DSHS relied upon to establish this Contract or Program Agreement are withdrawn, reduced or limited, or if additional or modified conditions are placed on such funding, after the effective date of this contract but prior to the normal completion of this Contract or Program Agreement:

  • For Lump Sum Change Order The payment and extension of time (if any) provided by this Change Order constitutes compensation in full to the Contractor and its Subcontractors and Suppliers for all costs and markups directly and indirectly attributable to the Change Order herein, for all delays related thereto and for performance of changes within the time stated.

  • Termination/Changes We reserve the right, in our sole discretion, to discontinue the provision of your electronic Communications, or to terminate or change the terms and conditions on which we provide electronic Communications. We will provide you with notice of any such termination or change as required by law.

  • CHANGE OF T-PIN The Account Holder may change his T-PIN from time to time in accordance with the Bank’s prescribed procedure then prevailing. The Bank shall be entitled, in its reasonable discretion but without liability and without giving any reason, to reject any selection made by the Account Holder as his substituted T-PIN; if the Bank so approves, such substituted T-PIN, shall take effect from the time of receipt by the Bank of such instructions from the Account Holder. The Account Holder shall take all steps not to select such numbers as a substitute T-PIN which may easily be ascertained or otherwise facilitate fraud or forgery.

  • TERMINATION OR MODIFICATION A. This Agreement shall continue in full force and effect until December 31, 2011.

  • Construction Change Directive A written order prepared and issued by the District, the Construction Manager, and/or the Architect and signed by the District and the Architect, directing a change in the Work.

  • Change of Use Alter or change the use of the Facility or enter into any management agreement for the Facility other than the Management Agreement or enter into any operating lease for the Facility, unless Borrower first notifies Lender and provides Lender a copy of the proposed lease agreement or management agreement, obtains Lender’s written consent thereto, which consent may be withheld in Lender’s sole discretion, and obtains and provides Lender with a subordination agreement in form satisfactory to Lender, as determined by Lender in its sole discretion, from such manager or lessee subordinating to all rights of Lender.