Common use of Preliminary Schedules Clause in Contracts

Preliminary Schedules. Within ten (10) business days of project award (unless otherwise specified in the General Requirements), Contractor shall submit to Architect for its timely review: 5.5.3.1 A preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 5.5.3.2 A preliminary schedule of Shop Drawings and Sample submittals which will list each required submittal and the times for submitting, reviewing, and processing such submittal; and 5.5.3.3 A preliminary Schedule of Values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. Accompanied with the Schedule of Values shall be a list of subcontractors who will be awarded each component of the work comprising the value of the Contract Price. The contractor shall not at any time substitute any subcontractor in place of any subcontractor listed as part of this requirement without the prior written permission of the Owner and Architect. The list shall identify which subcontractors are a Wyoming resident subcontract, or non-resident subcontractor and further illustrating that no less than 70% of the work comprising the value of the Contract Price will be awarded to Wyoming Resident Subcontractors. The requirement of this clause may be waived in part upon a written determination that: (I) The work to be performed is specialized or of such a scale that it can be more suitable performed by out-of-state contractors; (II) The bid amounts submitted by responsible Wyoming subcontractors exceed one hundred five percent (105%) of the costs of out-of-state providers for equivalent quality of work or services; (III) The enforcement of the requirement would unreasonably delay completion of construction; (IV) There were insufficient responsible Wyoming contractors submitting bids to make the seventy percent (70%) requirement; or (V) If the requirement of this clause is waived in part, the remaining value of the total subcontract work to be performed for the project is subject to the requirement of clause 5.5.3.3; (VI) Any waiver of clause 5.5.3.3 shall be approved in writing by the director of the School Facilities Division and the chairman of the board of the School Facilities Commission.

Appears in 4 contracts

Samples: Construction Agreement, Construction Agreement, Design Bid Build Contractor Services

AutoNDA by SimpleDocs

Preliminary Schedules. Within ten (10) business days of project award (unless otherwise specified in the General Requirements), Contractor shall submit to Architect for its timely review: 5.5.3.1 A preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 5.5.3.2 A preliminary schedule of Shop Drawings and Sample submittals which will list each required submittal and the times for submitting, reviewing, and processing such submittal; and 5.5.3.3 A preliminary Schedule of Values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. Accompanied with the Schedule of Values shall be a list of subcontractors who will be awarded each component of the work comprising the value of the Contract Price. The contractor shall not at any time substitute any subcontractor in place of any subcontractor listed as part of this requirement without the prior written permission of the Owner and Architect. The list shall identify which subcontractors are a Wyoming resident subcontract, or non-resident non‐resident subcontractor and further illustrating that no less than 70% of the work comprising the value of the Contract Price will be awarded to Wyoming Resident Subcontractors. The requirement of this clause may be waived in part upon a written determination that: (I) The work to be performed is specialized or of such a scale that it can be more suitable performed by out-of-state out‐of‐state contractors; (II) The bid amounts submitted by responsible Wyoming subcontractors exceed one hundred five percent (105%) of the costs of out-of-state out‐of‐state providers for equivalent quality of work or services; (III) The enforcement of the requirement would unreasonably delay completion of construction; (IV) There were insufficient responsible Wyoming contractors submitting bids to make the seventy percent (70%) requirement; or (V) If the requirement of this clause is waived in part, the remaining value of the total subcontract work to be performed for the project is subject to the requirement of clause 5.5.3.3; (VI) Any waiver of clause 5.5.3.3 shall be approved in writing by the director of the State Construction Department, School Facilities Division and the chairman of the board of the School Facilities Commission.

Appears in 3 contracts

Samples: Construction Agreement, Construction Agreement, Design Bid Build Contractor Services

Preliminary Schedules. Within ten (10) business days of project award (unless otherwise specified in the General Requirements), Contractor shall submit to Architect for its timely review: 5.5.3.1 A preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 5.5.3.2 A preliminary schedule of Shop Drawings and Sample submittals which will list each required submittal and the times for submitting, reviewing, and processing such submittal; and 5.5.3.3 A preliminary Schedule of Values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. Accompanied with the Schedule of Values shall be a list of subcontractors who will be awarded each component of the work comprising the value of the Contract Price. The contractor shall not at any time substitute any subcontractor in place of any subcontractor listed as part of this requirement without the prior written permission of the Owner and Architect. The list shall identify which subcontractors are a Wyoming resident subcontract, or non-resident subcontractor and further illustrating that no less than 70% of the work comprising the value of the Contract Price will be awarded to Wyoming Resident Subcontractors. The requirement of this clause may be waived in part upon a written determination that: (I) The work to be performed is specialized or of such a scale that it can be more suitable performed by out-of-state contractors; (II) The bid amounts submitted by responsible Wyoming subcontractors exceed one hundred five percent (105%) of the costs of out-of-state providers for equivalent quality of work or services; (III) The enforcement of the requirement would unreasonably delay completion of construction; (IV) There were insufficient responsible Wyoming contractors submitting bids to make the seventy percent (70%) requirement; or (V) If the requirement of this clause is waived in part, the remaining value of the total subcontract work to be performed for the project is subject to the requirement of clause 5.5.3.3; (VI) Any waiver of clause 5.5.3.3 shall be approved in writing by the director of the School Facilities Division Department and the chairman of the board of the School Facilities Commission.

Appears in 3 contracts

Samples: Design Bid Build Contractor Services, Construction Agreement, Construction Agreement

Preliminary Schedules. Within ten (10) business days of project award (unless otherwise specified in the General Requirements), Contractor shall submit to Architect for its timely review: 5.5.3.1 A preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 5.5.3.2 A preliminary schedule of Shop Drawings Drawing and Sample submittals which will list each required submittal and the times for submitting, reviewing, and processing such submittal; and 5.5.3.3 A preliminary Schedule schedule of Values values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. Accompanied with the Schedule schedule of Values values shall be a list of subcontractors who will be awarded each component of the work comprising the value of the Contract Price. The contractor shall not at any time substitute any subcontractor in place of any subcontractor listed as part of this requirement without the prior written permission of the Owner and Architect. The list shall identify identifying which subcontractors are a Wyoming resident subcontract, or non-resident subcontractor and further illustrating that no less than 70% of the work comprising the value of the Contract Price will be awarded to Wyoming Resident Subcontractors. The requirement of this clause may be waived in part upon a written determination that: (I) The work to be performed is specialized or of such a scale that it can be more suitable performed by out-of-state contractors; (II) The bid amounts submitted by responsible Wyoming subcontractors exceed one hundred five percent (105%) of the costs of out-of-state providers for equivalent quality of work or services; (III) The enforcement of the requirement would unreasonably delay completion of construction; (IV) There were insufficient responsible Wyoming contractors submitting bids to make the seventy percent (70%) requirement; or (V) If the requirement of this clause is waived in part, the remaining value of the total subcontract work to be performed for the project is subject to the requirement of clause 5.5.3.3; (VI) Any waiver of clause 5.5.3.3 shall be approved in writing by the director of the School Facilities Division and the chairman of the board of the School Facilities Commission5.

Appears in 2 contracts

Samples: Construction Agreement, Construction Agreement

AutoNDA by SimpleDocs

Preliminary Schedules. Within ten (10) business days of project award (unless otherwise specified in the General Requirements), Contractor shall submit to Architect for its timely review: 5.5.3.1 A preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 5.5.3.2 A preliminary schedule of Shop Drawings Drawing and Sample submittals which will list each required submittal and the times for submitting, reviewing, and processing such submittal; and 5.5.3.3 A preliminary Schedule schedule of Values values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. Accompanied with the Schedule schedule of Values values shall be a list of subcontractors who will be awarded each component of the work comprising the value of the Contract Price. The contractor shall not at any time substitute any subcontractor in place of any subcontractor listed as part of this requirement without the prior written permission of the Owner and Architect. The list shall identify identifying which subcontractors are a Wyoming resident subcontract, or non-resident subcontractor and further illustrating that no less than 70% of the work comprising the value of the Contract Price will be awarded to Wyoming Resident Subcontractors. The requirement of this clause may be waived in part upon a written determination that: (I) The work to be performed is specialized or of such a scale that it can be more suitable performed by out-of-state contractors; (II) The bid amounts submitted by responsible Wyoming subcontractors exceed one hundred five percent (105%) of the costs of out-of-state providers for equivalent quality of work or services; (III) The enforcement of the requirement would unreasonably delay completion of construction; (IV) There were insufficient responsible Wyoming contractors submitting bids to make the seventy percent (70%) requirement; or (V) If the requirement of this clause is waived in part, the remaining value of the total subcontract work to be performed for the project is subject to the requirement of clause 5.5.3.3; (VI) Any waiver of clause 5.5.3.3 shall be approved in writing by the director of the School Facilities Division school facilities Department and the chairman of the board of the School Facilities Commissionschool facilities Department.

Appears in 1 contract

Samples: Construction Agreement

Preliminary Schedules. Within ten (10) business days of project award (unless otherwise specified in the General Requirements), Contractor shall submit to Architect for its timely review: 5.5.3.1 A preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 5.5.3.2 A preliminary schedule of Shop Drawings and Sample submittals which will list each required submittal and the times for submitting, reviewing, and processing such submittal; and 5.5.3.3 A preliminary Schedule of Values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. Accompanied with the Schedule of Values shall be a list of subcontractors who will be awarded each component of the work comprising the value of the Contract Price. The contractor shall not at any time substitute any subcontractor in place of any subcontractor listed as part of this requirement without the prior written permission of the Owner and Architect. The list shall identify which subcontractors are a Wyoming resident subcontract, or non-resident subcontractor and further illustrating that no less than 70% of the work comprising the value of the Contract Price will be awarded to Wyoming Resident Subcontractors. The requirement of this clause may be waived in part upon a written determination that: (I) The work to be performed is specialized or of such a scale that it can be more suitable performed by out-of-state contractors; (II) The bid amounts submitted by responsible Wyoming subcontractors exceed one hundred five percent (105%) of the costs of out-of-state providers for equivalent quality of work or services; (III) The enforcement of the requirement would unreasonably delay completion of construction; (IV) There were insufficient responsible Wyoming contractors submitting bids to make the seventy percent (70%) requirement; or (V) If the requirement of this clause is waived in part, the remaining value of the total subcontract work to be performed for the project is subject to the requirement of clause 5.5.3.3; (VI) Any waiver of clause 5.5.3.3 shall be approved in writing by the director of the State Construction Department, School Facilities Division and the chairman of the board of the School Facilities Commission.

Appears in 1 contract

Samples: Construction Contract