Preparation of Works Schedule. 12.3.1 The Concessionaire will prepare: 12.3.1.1 an initial Works Schedule, which will be in all respects consistent with the Project Schedule, and will submit to the Province's Representative, in accordance with the Review Procedure, a copy of the same within 90 days of the Commencement Date; 12.3.1.2 a revised Works Schedule in respect of each revised Project Schedule submitted in accordance with Section 12.2.1, which will be in all respects consistent with the revised Project Schedule, and will submit to the Province's Representative, in accordance with the Review Procedure, a copy of the revised Works Schedule at the same time as the revised Project Schedule is submitted in accordance with Section 12.2.1; and 12.3.1.3 a revised Works Schedule in respect of each revision to the Project Schedule required by the Province pursuant to Section 12.2.2, which will be in all respects consistent with the revised Project Schedule, and will submit to the Province's Representative, in accordance with the Review Procedure, a copy of the revised Works Schedule as soon as practicable following notification of the change to the Project Schedule required by the Province. 12.3.2 Other than in the circumstances referred to in Section 12.3.1.2 or Section 12.3.1.3, if the Concessionaire wishes to make any amendment to the Works Schedule or if in the opinion of the Province's Representative or the Concessionaire at any time the actual progress of the Works does not conform with the Works Schedule then, prior to making any such amendment or within 15 days of being so required by the Province's Representative or (if earlier) becoming aware of such non-conformity, the Concessionaire will: 12.3.2.1 provide the Province's Representative with a report identifying the reasons for such amendment or non-conformity; and 12.3.2.2 submit to the Province's Representative in accordance with the Review Procedure a revised Works Schedule, which will be in all respects consistent with the Project Schedule. 12.3.3 The Province's Representative will be entitled to object to the initial Works Schedule or any revised Works Schedule on the grounds set out in paragraph 3.3 of Part 2 of Schedule 8 [Review Procedure]. 12.3.4 Subject to Section 12.4 [Works Schedule], the Works Schedule will be provided for the information of the Province and the Province's Representative. In the event of any conflict between the Project Schedule and the Works Schedule, the Project Schedule will (unless otherwise agreed by the Province in its absolute and unfettered discretion) prevail.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Preparation of Works Schedule. 12.3.1 The Concessionaire will prepare:
12.3.1.1 an initial Works Schedule, which will be in all respects consistent with the Project Schedule, and will submit to the Province's ’s Representative, in accordance with the Review Procedure, a copy of the same within 90 days of the Commencement Date;Date;
12.3.1.2 a revised Works Schedule in respect of each revised Project Schedule submitted in accordance with Section 12.2.1, which will be in all respects consistent with the revised Project Schedule, and will submit to the Province's ’s Representative, in accordance with the Review Procedure, a copy of the revised Works Schedule at the same time as the revised Project Schedule is submitted in accordance with Section 12.2.1; 12.2.1; and
12.3.1.3 a revised Works Schedule in respect of each revision to the Project Schedule required by the Province pursuant to Section 12.2.2, which will be in all respects consistent with the revised Project Schedule, and will submit to the Province's ’s Representative, in accordance with the Review Procedure, a copy of the revised Works Schedule as soon as practicable following notification of the change to the Project Schedule required by the Province.
12.3.2 Other than in the circumstances referred to in Section 12.3.1.2 or Section 12.3.1.3, if the Concessionaire wishes to make any material amendment to the Works Schedule or if in the opinion of the Province's ’s Representative or the Concessionaire at any time the actual progress of the design, construction, completion, commissioning and testing of the Works and the design and completion of the Decommissioning does not conform with the Works Schedule in a material respect then, prior to making any such amendment or within 15 14 days of being so required by the Province's ’s Representative or (if earlier) becoming aware of such non-conformity, the Concessionaire will:
12.3.2.1 provide the Province's ’s Representative with a report identifying the reasons for such amendment or non-conformity; conformity; and
12.3.2.2 submit to the Province's ’s Representative in accordance with the Review Procedure a revised Works Schedule, which will be in all respects consistent with the Project Schedule.
12.3.3 The Province's ’s Representative will be entitled to object to the initial Works Schedule or any revised Works Schedule only on the grounds set out in paragraph 3.3 of Part 2 of Schedule 8 [Review Procedure].
12.3.4 Subject to Section 12.4 [Works Schedule], the Works Schedule will be provided for the information of the Province and the Province's ’s Representative. In the event of any conflict between the Project Schedule and the Works Schedule, the Project Schedule will (unless otherwise agreed by the Province in its absolute and unfettered discretion) prevail.
Appears in 1 contract
Samples: Concession Agreement
Preparation of Works Schedule. 12.3.1 The Concessionaire will prepare:
12.3.1.1 an initial Works Schedule, which will be in all respects consistent with the Project Schedule, and will submit to the Province's ’s Representative, in accordance with the Review Procedure, a copy of the same within 90 days of the Commencement Date;Date;
12.3.1.2 a revised Works Schedule in respect of each revised Project Schedule submitted in accordance with Section 12.2.1, which will be in all respects consistent with the revised Project Schedule, and will submit to the Province's ’s Representative, in accordance with the Review Procedure, a copy of the revised Works Schedule at the same time as the revised Project Schedule is submitted in accordance with Section 12.2.1; 12.2.1; and
12.3.1.3 a revised Works Schedule in respect of each revision to the Project Schedule required by the Province pursuant to Section 12.2.2, which will be in all respects consistent with the revised Project Schedule, and will submit to the Province's ’s Representative, in accordance with the Review Procedure, a copy of the revised Works Schedule as soon as practicable following notification of the change to the Project Schedule required by the Province.
12.3.2 Other than in the circumstances referred to in Section 12.3.1.2 or Section 12.3.1.3, if the Concessionaire wishes to make any material amendment to the Works Schedule or if in the opinion of the Province's ’s Representative or the Concessionaire at any time the actual progress of the design, construction, completion, commissioning and testing of the Works and the design and completion of the Decommissioning does not conform with the Works Schedule in a material respect then, prior to making any such amendment or within 15 14 days of being so required by the Province's ’s Representative or (if earlier) becoming aware of such non-conformitynonconformity, the Concessionaire will:
12.3.2.1 provide the Province's ’s Representative with a report identifying the reasons for such amendment or non-conformity; nonconformity; and
12.3.2.2 submit to the Province's ’s Representative in accordance with the Review Procedure a revised Works Schedule, which will be in all respects consistent with the Project Schedule.
12.3.3 The Province's ’s Representative will be entitled to object to the initial Works Schedule or any revised Works Schedule only on the grounds set out in paragraph 3.3 of Part 2 of Schedule 8 [Review Procedure].
12.3.4 Subject to Section 12.4 [Works Schedule], the Works Schedule will be provided for the information of the Province and the Province's ’s Representative. In the event of any conflict between the Project Schedule and the Works Schedule, the Project Schedule will (unless otherwise agreed by the Province in its absolute and unfettered discretion) prevail.
Appears in 1 contract
Samples: Concession Agreement