PRODUCTION NOTICE. 9.1 The Operator shall call a Management Committee meeting to consider the Feasibility Report for a date no sooner than three months and no later than six months after the Feasibility Report was provided to each of the parties. 9.2 The Management Committee shall consider the Feasibility Report prepared and may approve the Feasibility Report, with such modifications, if any, as it considers necessary or desirable, together with an estimate of Construction Costs. If a Feasibility Report is approved as aforesaid the Management Committee shall forthwith cause a Production Notice to be given to each of the parties by the Operator stating that the Management Committee has approved that a Mine be established and brought into production in conformity with the Feasibility Report and estimated Construction Costs as so approved.
Appears in 4 contracts
Samples: Mining Option Agreement (All American Gold Corp.), Option Agreement (Source Gold Corp.), Joint Venture Agreement (Source Gold Corp.)
PRODUCTION NOTICE. 9.1 The Operator shall call a Management Committee meeting to consider the Feasibility Report for a date no sooner than three months and no later than six months months, after the Feasibility Report was provided to each of the parties.
9.2 The Management Committee shall consider the Feasibility Report prepared and may by Special Majority, approve the Feasibility Report, with such modifications, if any, as it considers necessary or desirable, together with an estimate of Construction Costs. If a Feasibility Report is approved as aforesaid the Management Committee shall forthwith cause a Production Notice to be given to each of the parties by the Operator stating that the Management Committee has approved that a Mine be established and brought into production in conformity with the Feasibility Report and estimated Construction Costs Casts as so approved.
Appears in 2 contracts
Samples: Mining Agreement (Mexoro Minerals LTD), Mining Agreement (Sunburst Acquisitions Iv Inc)
PRODUCTION NOTICE. 9.1 The Operator shall call a Management Committee meeting to consider the Feasibility Report for a date no sooner than three months and no later than six months after the Feasibility Report was provided to each of the parties.
9.2 The Management Committee shall consider the Feasibility Report prepared and may by Special Majority, approve the Feasibility Report, with such modifications, if any, as it considers necessary or desirable, together with an estimate of Construction Costs. If a Feasibility Report is approved as aforesaid the Management Committee shall forthwith cause a Production Notice to be given to each of the parties by the Operator stating that the Management Committee has approved that a Mine be established and brought into production in conformity with the Feasibility Report and estimated Construction Costs as so approved.
Appears in 2 contracts
Samples: Mining Option Agreement (Coastal Pacific Mining Corp), Mining Option Agreement (Pana-Minerales S.A.)
PRODUCTION NOTICE. 9.1 9.01 The Operator shall call a Management Committee meeting to consider the Feasibility Report for a date no sooner than three months and no later than six months after the Feasibility Report was provided to each of the parties.
9.2 9.02 The Management Committee shall consider the Feasibility Report prepared and may by Special Majority, approve the Feasibility Report, with such modifications, if any, as it considers necessary or desirable, together with an estimate of Construction Costs. If a Feasibility Report is approved as aforesaid the Management Committee shall forthwith cause a Production Notice to be given to each of the parties by the Operator stating that the Management Committee has approved that a Mine be established and brought into production in conformity with the Feasibility Report and estimated Construction Costs as so approved.
Appears in 1 contract
PRODUCTION NOTICE. 9.1 The Operator shall call a Management Committee meeting to consider the Feasibility Report for a date no sooner than three months and no later than six months (unless otherwise agreed by the parties) after the Feasibility Report was provided to each of the partiesParticipants.
9.2 The Management Committee shall consider the Feasibility Report prepared and may by Special Majority, approve the Feasibility Report, with such modifications, if any, as it considers necessary or desirable, together with an estimate of Construction Costs. If a Feasibility Report is approved as aforesaid the Management Committee shall forthwith cause a Production Notice to be given to each of the parties Participants by the Operator stating that the Management Committee has approved that a Mine be established and brought into production in conformity with the Feasibility Report and estimated Construction Costs as so approved.
Appears in 1 contract
PRODUCTION NOTICE. 9.1 9.01 The Operator shall call a Management Committee meeting to consider the Feasibility Report for a date no sooner than three months and no later than six months after the Feasibility Report was provided to each of the parties.
9.2 9.02 The Management Committee shall consider the Feasibility Report prepared and may by Special Majority, approve the Feasibility Report, with such modificationsmodi-fications, if any, as it considers necessary or desirable, together with an estimate of Construction Costs. If a Feasibility Report is approved as aforesaid the Management Committee shall forthwith cause a Production Notice to be given to each of the parties by the Operator stating that the Management Committee has approved that a Mine be established and brought into production in conformity with the Feasibility Report and estimated Construction Costs as so approved.
Appears in 1 contract
Samples: Property Option Agreement (Revelstoke Industries, Inc.)
PRODUCTION NOTICE. 9.1 9.01 The Operator shall call a Management Committee meeting to consider the Feasibility Report for a date no sooner than three months and no later than six months after the Feasibility Report was provided to each of the parties.
9.2 9.02 The Management Committee shall consider the Feasibility Report prepared and by Special Majority, may approve the Feasibility Report, with such modifications, if any, as it considers necessary or desirable, together with an estimate of Construction Costs. If a Feasibility Report is approved as aforesaid the Management Committee shall forthwith cause a Production Notice to be given to each of the parties by the Operator stating that the Management Committee has approved that a Mine be established and brought into production in conformity with the Feasibility Report and estimated Construction Costs as so approved.