PROGRAM TO BE SUBMITTED. 10.1 The Contractor shall within 14 (fourteen) days of the date of this Contract submit to UNICEF a program for the execution of the Works. The program should contain all activities required to carry out the Works, and specifically note all critical activities, including critical path, and critical inspection points. 10.2 If at any time, it should appear that the actual progress of the work does not conform to the program, a revised program shall be submitted, showing modifications necessary to ensure completion on time. 10.3 Submission by the Contractor and acceptance by UNICEF of such program or revised program shall not relieve the Contractor of any of their duties or responsibilities under the Contract.
Appears in 6 contracts
Samples: Contract for Construction Works, Construction Contract, Construction Contract