PROGRAMME AND DATES FOR COMPLETION Dates for Completion. 14.1 DBFM Co shall complete the Works [relating to a Phase] by the Completion Date [relevant Phase Completion Date]. Without prejudice to Clauses 40 (DBFM Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date]. The Programme
Appears in 5 contracts
Samples: Project Agreement, Project Agreement, www.scottishfuturestrust.org.uk
PROGRAMME AND DATES FOR COMPLETION Dates for Completion. 14.1 DBFM Co shall complete the Works [relating to a Phase] by the Completion Date [relevant Phase Completion Date]. Without prejudice to Clauses 40 (DBFM Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date]. The Programme
Appears in 1 contract
Samples: Agreement
PROGRAMME AND DATES FOR COMPLETION Dates for Completion. 14.1 DBFM Co shall complete the Works [relating to a Phase] Phase by the Completion Date [relevant Phase Completion Date]. Without prejudice to Clauses 40 (DBFM Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the relevant Phase Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date]. The Programme
Appears in 1 contract
Samples: Agreement