PROGRAMME AND DATES FOR COMPLETION Dates for Completion. 14.1 Sub-hubco shall complete the Works [relating to a Phase] by the Completion Date [relevant Phase Completion Date]. Without prejudice to Clauses 40 (Sub-hubco Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date]. The Programme
Appears in 2 contracts
Samples: www.scottishfuturestrust.org.uk, www.scottishfuturestrust.org.uk
PROGRAMME AND DATES FOR COMPLETION Dates for Completion. 14.1 Sub-hubco Project Co shall complete the Works [relating to a Phase] by the [Completion Date Date] [relevant Phase Completion Date]. Without prejudice to Clauses 40 Clause 44 (Sub-hubco Project Co Event of Default), 42 46 (Authority Voluntary Termination), 46 50 (Compensation on Termination) and 47 51 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the [Completion Date Date] [Phase Completion Date] and the [Actual Completion Date Date] [relevant Phase Actual Completion Date]. The Programme
Appears in 1 contract
Samples: llyw.cymru
PROGRAMME AND DATES FOR COMPLETION Dates for Completion. 14.1 Sub-hubco shall complete the Works [relating to a Phase] by the Completion Date [relevant Phase Completion Date]. Without prejudice to Clauses 40 (Sub-hubco Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date]. The Programme
Appears in 1 contract
Samples: Agreement