Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least three (3) years experience in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also the Contractor shall provide licenced copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 75 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least three (3) years experience years’ experiences in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also the Contractor shall provide licenced licensed copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least three (3) years experience in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also the Contractor shall provide licenced copy Contract AgreementPage 65 of software used to develop Works Programme to the Authority and Authority’s Engineer.159
Appears in 1 contract
Samples: Contract Agreement
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least three (3) years experience in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also the Contractor shall provide licenced copy of software used to develop Works Programme to the Authority and Authority’s Engineer.provide
Appears in 1 contract
Samples: Contract Agreement
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Organization Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least three (3) years experience years’ experiences in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also Also, the Contractor shall provide licenced licensed copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 1 contract
Samples: Construction Contract
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least atleast three (3) years experience in such work. The programmers shall be employed by employedby the Contractor full time on the Contract until the completion or such earlier time the timethe Engineer may give his consent. Also the Contractor shall provide licenced copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 1 contract
Samples: Construction Contract
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least three (3) years experience in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also the Contractor shall provide State of Manipur” November 2020 licenced copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 1 contract
Samples: Contract Agreement
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required re- quired information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming program- ming civil engineering works. Others in the group shall have at least three (3) years experience ex- perience in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also the Contractor shall provide licenced copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 1 contract
Samples: Construction Contract
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. .The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. .Others in the group shall have at least three (3) years experience in such work. .The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the timethe Engineer may give his consent. Also the Contractor shall provide licenced copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 1 contract
Samples: Construction Contract
Programming Personnel and Software. The Contractor shall submit, as part of its Staff Organisation Plan, the names and required information for the staff to be employed on Works Programming. The principal Works Programmer shall hold reputable professional qualifications acceptable to the Authority’s Engineer including at least five (5) years relevant experience in programming civil engineering works. Others in the group shall have at least three (3) years experience in such work. The programmers shall be employed by the Contractor full time on the Contract until the completion or such earlier time the Engineer may give his consent. Also the Contractor shall provide licenced licensed copy of software used to develop Works Programme to the Authority and Authority’s Engineer.
Appears in 1 contract
Samples: Construction Contract