Project Implementation Schedule. 6.3.1 The Developer shall in accordance with the terms and conditions of this agreement submit to NRDA for its approval Project Implementation methodology, Construction Milestones and time schedule within 60 days from the date of this agreement 6.3.2 The whole of the work under the project shall be carried out strictly in accordance with the scope indicated in this Agreement, and as per the following: 1) National Building Code 2) Codes & Standards of Bureau of Indian standards
Appears in 2 contracts
Samples: Grant of Development Rights for Group Housing Development, Grant of Development Rights for Group Housing Development
Project Implementation Schedule. 6.3.1 The Developer Lessee shall in accordance with the terms and conditions of this agreement submit to NRDA for its approval of Project Implementation methodology, Construction Milestones and time schedule within 60 days from the date of this agreement
6.3.2 The whole of the work under the project shall be carried out strictly in accordance with the scope indicated in this Agreement, and as per the following:
1) National Building Code 2) Codes & Standards of Bureau of Indian standards
Appears in 1 contract
Samples: Lease Agreement
Project Implementation Schedule. 6.3.1 The Developer Lessee shall in accordance with the terms and conditions of this agreement submit to NRDA for its approval of Project Implementation methodology, Construction Milestones and time schedule within 60 days from the date of this agreement
6.3.2 The whole of the work under the project shall be carried out strictly in accordance with the scope indicated in this Agreement, and as per the following:
: 1) National Building Code 2) Codes & Standards of Bureau of Indian standardsstandards 3) In case of difficulty in implementation, any other standard specification approved by the steering Group The Lessee shall adhere to the above specification given above in same order of preference.