Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Site permits. On or before September 15, 2022, Interconnection Customer must demonstrate that it has obtained any necessary local, county and state site permits. 6.2 Acquisition of major electrical equipment. On or before November 23, 2021, Interconnection Customer must demonstrate that it has signed a memorandum of understanding for the acquisition of major equipment. 6.3 Substantial Site work completed. On or before October 17, 2022, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.4 Delivery of major electrical equipment. On or before January 16, 2023, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.
Appears in 1 contract
Samples: Interconnection Service Agreement
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones:
6.1 Site permits. On or before September 15February 28, 20222023, Interconnection Customer must demonstrate that it has obtained any necessary local, county county, and state site permits.
6.2 Acquisition of major electrical equipment. On or before November 23December 31, 20212024, Interconnection Customer must demonstrate that it has signed a memorandum of understanding for the acquisition of major equipment.
6.3 Substantial Site work completed. On or before October 17September 30, 20222025, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities.
6.4 Delivery of major electrical equipment. On or before January 16September 30, 20232025, Interconnection Customer must demonstrate that all 75 MWac generating units have been delivered to Interconnection Customer’s project site.
Appears in 1 contract
Samples: Interconnection Service Agreement
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones:
6.1 Site permits. On or before September 15January 31, 20222024, Interconnection Customer must demonstrate that it has obtained any all necessary local, county county, and state site permits.
6.2 Acquisition of major electrical equipment. On or before November 23January 31, 20212024, Interconnection Customer must demonstrate that it has signed a memorandum of understanding for the acquisition of major equipment.
6.3 Substantial Site work completed. On or before October 17April 15, 2022, 2024 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities.
6.4 Delivery of major electrical equipment. On or before January 16June 30, 20232024, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.
Appears in 1 contract
Samples: Interconnection Service Agreement
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones:
6.1 Site permits. On or before September 1530, 2022, Interconnection Customer must demonstrate that it has obtained any all necessary local, county county, and state site permits.
6.2 Acquisition of major electrical equipment. On or before November 23October 31, 20212022, Interconnection Customer must demonstrate that it has signed a memorandum of understanding for the acquisition of major equipment.
6.3 Substantial Site work completed. On or before October 17December 31, 2022, 2023 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities.
6.4 Delivery of major electrical equipment. On or before January 16March 31, 2023, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.
Appears in 1 contract
Samples: Interconnection Service Agreement